Contract No: HK/2011/07 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 2) Environmental Permit no. EP-364/2009/D, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B Monthly Environmental Monitoring &
Audit Report
- December 2015 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
14 January 2016 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3.
status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7.
Cumulative Construction Impact due to the Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.3 Summary
of submission status under FEP-02/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.5 Summary
of submission status under FEP-01/364/2009
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary
of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under FEP-09/364/2009/B
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/B
Table 4.1 Noise Monitoring
Stations
Table 4.2 Real
Time Noise Monitoring Stations
Table 4.3 Air
Quality Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real
Time Noise Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air
Quality Monitoring Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring
Station for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring
Station for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring
Stations for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections for
Contract no. HY/2009/18
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of Environmental Inspections for Contract
no. HK/2012/08
Table 8.7 Summary of Environmental Inspections for Contract no. HY/2010/08
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Drainage works
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 1 & 2 Backfilling works at CWB Tunnel top slab
¡P
Construction of slip road 2 and slip road 3
¡P
Stage 3 RC structure for CWB Tunnel Bay 18 to 20
¡P
Removal of abandoned cooling main (P7/P9) at Convention Avenue
¡P
Reinstatement of outfall was
¡P
Reinstatement of triangular planter at Fenwick Pier Street
¡P
Roadworks /drains for Expo Drive East
¡P
Stage 4 ELS works
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Removal of stockpile of material, site clearance works at Tunnel Portion
1.
¡P
Construction of road side barriers
¡P
Backfilling works and access shaft construction
¡P
Construction of road side barriers
¡P
Struts installation for
layer S6
¡P
Excavation for layer S6 and formation level
¡P
Construction of blinding layer
¡P
Breaking through bulkhead wall BW3
¡P
Ground investigation works
¡P
Bored pile construction
¡P
Extraction of the temporary sheet pile seawall and removal of the
temporary seawall blocks near the interface between Portion 2 and Portion 5.
¡P
Setting up of silo tanks, pre-treatment works for diaphragm wall
construction
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Construction roadside barrier at Mined Tunnel
¡P
Rock excavation at TPCWAW
¡P
Demolition of bulkhead wall between TPCWAE and TPCWAW
¡P
Construction RC structure at TPCWAW
¡P
Remaining works inside tunnel at TS4 and TPCWAE
¡P
Removal of standby Dewatering System and monitoring instrument along
Hung Hing road
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Pier construction for IEC
¡P
Construction of EVB
¡P
Column modification at F1 to F8
¡P
Bridge E deck construction
¡P
Watson Road laying of new water pipe
¡P
Oil Street drainage works
¡P
Excavation / Construction of retaining wall/Approach Ramp /ADB
¡P
Bridge segment erections
¡P
Pre-bored H-pile for Approach Ramp
¡P
Hing Fat Street modification works
¡P
Bridge TA2 demolition
¡P
Abutment D12 construction
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
¡P
Diaphragm wall construction
¡P
Grouting
¡P
Construction of MVB
¡P
Pre-bored H-pile construction
¡P
Construction of concrete plug
¡P
Excavation and lateral support installation
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009B
¡P
Tree protection works next to existing BGO,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Pipe piling & grouting works,
¡P
Utility diversion works,
¡P
Retaining wall works
¡P
ELS works,
¡P
Diaphragm Wall, Barrette construction and king post installation works
¡P
D-wall drill cutting works
¡P
Construction works for subway extension
Contract
no. HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
West Ventilation Building Construction
¡P
East Ventilation Shaft Construction
¡P
Tunnel Thermal Barrier Construction
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
ET confirmed with the Resident Site
Staff that bridge works and drains/ sewers construction at the concerned
location was undertaken by Contract HY/2009/18 on 12 November 2015. A stockpile which would be reused for
backfilling was stored at the concerned location by Contract HY/2009/18 on 12
November 2015.
Mitigation measures implemented by the
Contractor for the above construction works including covering of idled portion
of stockpile and dampening of the exposed stockpile was implemented for the
stockpile at the concerned location.
According to relevant site records
confirmed by RSS, bridge works and drains/ sewers construction at the concerned
location was undertaken by Contractor of HY/2009/18 on 12 November 2015 and a
stockpile which would be reused for backfilling was stored at the concerned
location. Mitigation measures including covering of idled portion of stockpile
and dampening of the exposed stockpile was implemented for the stockpile at the
concerned location.
In view of the public concern on
potential dust impact at the concerned location, the Contractor of HY/2009/18
rearranged the works sequence and placed concrete blocks at the bridge
retaining wall to allow for early commencement of backfilling on 19 November
2015 to minimize the size of the stockpile at an earlier stage. Additional
water sprinklers were installed on 27 November 2015 to further enhance the
dampening of the stockpile surface during excavation.
Follow-up inspection was conducted
during weekly environmental inspection on 10 December 2015 and mitigation
measures including covering of stockpile stored at the concerned location was
implemented while it was observed that stockpiles stored near Man Chiu Street
was not properly covered. The Contractor of HY/2009/18 was advised to promptly
provide covering to all idled stockpile stored on site and the Contractor was
reminded to enhance the watering during excavated material handling near the
concerned location. Further follow up inspection was conducted on 17 December
2015 and mitigation measures including covering and watering for idle stockpile
and material handling were implemented.
Over the past couple of weeks, there
have been loud mechanical pounding at the construction site over the reclaimed
area between Blocks 10 and 11 of City Garden. As can be seen, machines have
been breaking open the concrete paved on top of the reclaimed area. Work often
starts well before 9am on weekdays and, barring a brief period of lull during
lunch hours, would often continue unabated until after 5pm. Although I note
that certain noise reduction measures have been put into place (e.g. the
erection of flimsy noise barriers around the work area), the noise created is
still enormous, and this has become a significant nuisance for residents living
in nearby blocks of our estate, especially children and the elderly who have to
stay at home for longer hours.
ET confirmed with the Resident Site
Staff that concreting breaking works was carried out with one breaker on 7, 9,
11, 12 and 14 December 2015 and the breaking works at the concerned location
were completed on 14 December 2015 morning. Noise mitigation measures including
temporary noise barriers near the point of breaking and covering the breaker
with acoustic mat were provided during the concerned concrete breaking works.
According to information confirmed by
RSS, concreting breaking works was carried out by one excavator mounted breaker
on 7, 9, 11, 12 and 14 December 2015 and the concerned breaking works outside
City Garden Block 10 and Block 11 was completed on 14 December 2015 morning.
Noise mitigation measures including temporary noise barriers near the point of
breaking and covering the breaker with acoustic mat were provided during the
concerned concrete breaking works. Based on the further review on the record of
the environmental inspection conducted on 09 December 2015, the Contractor of
HY/2009/19 was reminded to temporary noise barrier provided for the pile cap demolition
shall follow the Environmental Permit EP-364/2009/D requirement.
Follow up inspection was conducted
during weekly environmental inspection on 17 December 2015, the concerned
breaking works opposite to City Garden Block 10 and Block 11 was observed
completed while the Contractor was reminded that the remaining section of
temporary noise barrier in accordance with the latest Environmental Permit
EP-364/2009/D shall be completed on site as soon as possible. According to the
information provided by RSS, the temporary noise barrier in accordance with the
Environmental Permit requirement opposite to City Garden was substantially
completed on 21 December 2015. In view of the public concern, the Contractor
was suggested to consider to review the works duration at daytime and conduct
other future breaking works around the concerned location intermittently to
minimize the potential noise nuisance caused to the surroundings.
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Drainage works
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
¡P
Stage 1 ,2 & 3 Backfilling works at CWB Tunnel top slab
¡P
Stage 2 Construction of slip road 3
¡P
Stage 3 RC structure for CWB Tunnel Bay 18 to 20
¡P
Removal of abandoned cooling main (P7/P9) at Convention Avenue
¡P
Reinstatement of outfall
¡P
Reinstatement of triangular planter at Fenwick Pier Street
¡P
Roadworks /drains for Expo Drive East
¡P
Stage 4 ELS works
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Completion of road side barriers
¡P
Backfilling works
¡P
Cutting the top part of diaphragm wall
¡P
Strut layer S6 lateral support installation
¡P
Breaking through bulkhead wall BW3
¡P
Pouring blinding layer concrete
¡P
Tunnel construction at west side
¡P
Waterproofing layer application
¡P
Ground investigation works for bored piles and diaphragm wall
¡P
Bored pile construction
¡P
Pre-treatment works and guide wall construction for diaphragm wall
¡P
Diaphragm wall construction
¡P
Extraction of the temporary sheetpile seawall and removal of the
temporary seawall blocks near the interface between Portion 2 and Portion 5
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Remedial works at Mined Tunnel
¡P
Excavation and RC structure works at TPCWAW
¡P
Remaining works inside tunnel at TS4 and TPCWAE
¡P
Removal of standby Dewatering System and monitoring instrument along
Hung Hing road
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Construction of EVB
¡P
Column modification at F1 to F8
¡P
Watson Road laying of new water pipe
¡P
Oil Street drainage works
¡P
Excavation / Construction of retaining wall/Approach Ramp/ADB
¡P
Bridge segment erections
¡P
Pre-bored H-pile for Approach Ramp
¡P
Hing Fat Street modification works
¡P
Bridge TA2 demolition
¡P
Abutment D12 construction
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
¡P
Diaphragm wall construction
¡P
Grouting
¡P
Construction of MVB
¡P
Pre-bored H-pile construction
¡P
Construction of concrete plug
¡P
Excavation and lateral support installation
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree protection works next to existing BGO,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Pipe piling & grouting works,
¡P
Utility diversion works,
¡P
Retaining wall works
¡P
ELS works,
¡P
Diaphragm Wall, Barrette construction and king post installation works
¡P
D-wall drill cutting works
¡P
Construction works for subway extension
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
West Ventilation Building Construction
¡P
East Ventilation Shaft Construction
¡P
Tunnel Thermal Barrier Construction
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/C and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/C, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B
during the period 28 November 2015 to 26 December 2015.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
¡P
Tunnel control buildings and ventilation buildings;
¡P
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
¡P
Associated road lighting, road signing, traffic control and surveillance
system; and
¡P
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ¡V Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ¡VTunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2634
1626 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr.
Terry Tsang |
6683
9394 |
|||
Environmental
Officer |
Ms. Wendy
Ng |
9803
0057 |
|||
Assistant
Environmental Engineer |
Ms. Connie Chan |
6157 7057 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570
8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
|
Deputy Site Agent |
Mr. Bob Yeung |
2214
7703 |
|||
Environmental Officer |
Ms. Lighting Chan |
2823
1161 |
|||
Assistant Environmental Engineer |
Mr. Christy So |
3937
1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Andrew Wong |
3557
6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
2566
8061 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dr. Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
Mr. C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Mr. Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823 1111 |
21406799 |
Site
Agent |
Colman Wong |
9730 0806 |
|||
Environmental
Officer |
Malcom
Leung |
3973 0850 |
|||
Environmental
Supervisor |
Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
¡P
Drainage works
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 1 & 2 Backfilling works at CWB Tunnel top slab
¡P
Construction of slip road 2 and slip road 3
¡P
Stage 3 RC structure for CWB Tunnel Bay 18 to 20
¡P
Removal of abandoned cooling main (P7/P9) at Convention Avenue
¡P
Reinstatement of outfall was
¡P
Reinstatement of triangular planter at Fenwick Pier Street
¡P
Roadworks /drains for Expo Drive East
¡P
Stage 4 ELS works
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Removal of stockpile of material, site clearance works at Tunnel Portion
1.
¡P
Construction of road side barriers
¡P
Backfilling works and access shaft construction
¡P
Construction of road side barriers
¡P
Struts installation for
layer S6
¡P
Excavation for layer S6 and formation level
¡P
Construction of blinding layer
¡P
Breaking through bulkhead wall BW3
¡P
Ground investigation works
¡P
Bored pile construction
¡P
Extraction of the temporary sheet pile seawall and removal of the
temporary seawall blocks near the interface between Portion 2 and Portion 5.
¡P
Setting up of silo tanks, pre-treatment works for diaphragm wall
construction
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Construction roadside barrier at Mined Tunnel
¡P
Rock excavation at TPCWAW
¡P
Demolition of bulkhead wall between TPCWAE and TPCWAW
¡P
Construction RC structure at TPCWAW
¡P
Remaining works inside tunnel at TS4 and TPCWAE
¡P
Removal of standby Dewatering System and monitoring instrument along
Hung Hing road
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
¡P
Pier construction for IEC
¡P
Construction of EVB
¡P
Column modification at F1 to F8
¡P
Bridge E deck construction
¡P
Watson Road laying of new water pipe
¡P
Oil Street drainage works
¡P
Excavation / Construction of retaining wall/Approach Ramp /ADB
¡P
Bridge segment erections
¡P
Pre-bored H-pile for Approach Ramp
¡P
Hing Fat Street modification works
¡P
Bridge TA2 demolition
¡P
Abutment D12 construction
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
¡P
Diaphragm wall construction
¡P
Grouting
¡P
Construction of MVB
¡P
Pre-bored H-pile construction
¡P
Construction of concrete plug
¡P
Excavation and lateral support installation
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree protection works next to existing BGO,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Pipe piling & grouting works,
¡P
Utility diversion works,
¡P
Retaining wall works
¡P
ELS works,
¡P
Diaphragm Wall, Barrette construction and king post installation works
¡P
D-wall drill cutting works
¡P
Construction works for subway extension
Contract no. HY/2011/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
West Ventilation Building Construction
¡P
East Ventilation Shaft Construction
¡P
Tunnel Thermal Barrier Construction
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract
no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
¡P
Drainage works
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
¡P
Stage 1 ,2 & 3 Backfilling works at CWB Tunnel top slab
¡P
Stage 2 Construction of slip road 3
¡P
Stage 3 RC structure for CWB Tunnel Bay 18 to 20
¡P
Removal of abandoned cooling main (P7/P9) at Convention Avenue
¡P
Reinstatement of outfall
¡P
Reinstatement of triangular planter at Fenwick Pier Street
¡P
Roadworks /drains for Expo Drive East
¡P
Stage 4 ELS works
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Completion of road side barriers
¡P
Backfilling works
¡P
Cutting the top part of diaphragm wall
¡P
Strut layer S6 lateral support installation
¡P
Breaking through bulkhead wall BW3
¡P
Pouring blinding layer concrete
¡P
Tunnel construction at west side
¡P
Waterproofing layer application
¡P
Ground investigation works for bored piles and diaphragm wall
¡P
Bored pile construction
¡P
Pre-treatment works and guide wall construction for diaphragm wall
¡P
Diaphragm wall construction
¡P
Extraction of the temporary sheetpile seawall and removal of the
temporary seawall blocks near the interface between Portion 2 and Portion 5
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Remedial works at Mined Tunnel
¡P
Excavation and RC structure works at TPCWAW
¡P
Remaining works inside tunnel at TS4 and TPCWAE
¡P
Removal of standby Dewatering System and monitoring instrument along
Hung Hing road
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Pier construction for IEC
¡P
Construction of EVB
¡P
Column modification at F1 to F8
¡P
Watson Road laying of new water pipe
¡P
Oil Street drainage works
¡P
Excavation / Construction of retaining wall/Approach Ramp/ADB
¡P
Bridge segment erections
¡P
Pre-bored H-pile for Approach Ramp
¡P
Hing Fat Street modification works
¡P
Bridge TA2 demolition
¡P
Abutment D12 construction
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B
¡P
Diaphragm wall construction
¡P
Grouting
¡P
Construction of MVB
¡P
Pre-bored H-pile construction
¡P
Construction of concrete plug
¡P
Excavation and lateral support installation
Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip
Road 8) under FEP-10/364/2009
¡P
Tree protection works next to existing BGO,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Pipe piling & grouting works,
¡P
Utility diversion works,
¡P
Retaining wall works
¡P
ELS works,
¡P
Diaphragm Wall, Barrette construction and king post installation works
¡P
D-wall drill cutting works
¡P
Construction works for subway extension
Contract no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡VTunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
¡P
West Ventilation Building Construction
¡P
East Ventilation Shaft Construction
¡P
Tunnel Thermal Barrier Construction
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2015 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further Environmental Permit |
24 Nov 2015 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS0706-15 |
30 Jun 2015 |
02 Jul 2015 to 01 Jan 2016 |
Valid |
|
GW-RS0803-15 |
28 Jul 2015 |
21 Aug 2015 to 20 Feb 2016 |
Valid |
|
GW-RS0804-15 |
28 Jul 2015 |
22 Aug 2015 to 21 Feb 2016 |
Valid |
|
GW-RS0868-15 |
13 Aug 2015 |
14 Aug 2015 to 13 Feb 2016 |
Valid |
GW-RS1025-15 |
22 Sep 2015 |
24 Sep 2015 to 23 Mar 2016 |
Valid |
|
GW-RS1031-15 |
22 Sep 2015 |
29 Sep 2015 to 24 Mar 2016 |
Cancelled |
|
|
GW-RS1134-15 |
23 Oct 2015 |
08 Nov 2015 to 07 May 2016 |
Valid |
|
GW-RS1135-15 |
23 Oct 2015 |
26 Nov 2015 to 25 May 2016 |
Valid |
|
GW-RS1228-15 |
13 Nov 2015 |
16 Nov 2015 to 13 May 2016 |
Valid |
|
GW-RS1309-15 |
27 Nov 2015 |
30 Nov 2015 to 26 May 2016 |
Valid |
Discharge Licence |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP_MD_16-018 |
02 Jun 2015 |
13 Oct 2015 to 12 Apr 2016 |
Valid |
Table 3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May
2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun
2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar
2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS0723-15 |
2 Jul 2015 |
7 July 2015 to 06 Jan 2016 |
Cancelled |
GW-RS0831-15 |
31 Jul 2015 |
03 Aug 2015 to 28 Jan 2016 |
Cancelled |
|
GW-RS0610-15 |
10 Jun 2015 |
22 Jun 2015 to 21 Dec 2015 |
Expired |
|
GW-RS0637-15 |
11 Jun 2015 |
18 Jun 2015 to 08 Dec 2015 |
Expired |
|
GW-RS0709-15 |
30 Jun 2015 |
02 July 2015 to 01 Jan 2016 |
Valid |
|
GW-RS0716-15 |
30 Jun 2015 |
04 July 2015 to 27 Dec 2015 |
Expired |
|
GW-RS0981-15 |
07 Sep 2015 |
09 Sep 2015 to 06 Mar 2016 |
Cancelled |
|
GW-RS1004-15 |
15 Sep 2015 |
17 Sep 2015 to 16 Dec 2015 |
Expired |
|
GW-RS1006-15 |
15 Sep 2015 |
18 Sep 2015 to 14 Mar 2016 |
Valid |
|
GW-RS1099-15 |
08 Oct 2015 |
08 Oct 2015 to 30 Nov 2015 |
Expired |
|
GW-RS1121-15 |
20 Oct 2015 |
22 Oct 2015 to 18 Apr 2016 |
Cancelled |
|
GW-RS1150-15 |
26 Oct 2015 |
28 Oct 2015 to 27 Apr 2016 |
Valid |
|
GW-RS1187-15 |
28 Oct 2015 |
30 Oct 2015 to 27 Apr 2016 |
Valid |
|
GW-RS1413-15 |
24 Dec 2015 |
02 Jan 2016 to 01 Jul 2016 |
Valid |
|
Water
Discharge License |
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
WT00009691-2011 |
01 Aug 2011 |
31 July 2016 |
Valid |
|
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping
Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/16-034 |
26 Jun 2015 |
01 Jul 2015 to 31 Dec 2015 |
Valid |
EP/MD/16-146 |
24 Dec 2015 |
01 Jan 2016 to 30 Jun 2016 |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP
Condition |
Submission |
Date of Submission |
Condition
2.7 and 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Condition
2.6 |
Environmental Management
Organization Chart |
14 Jun
2011 |
Condition
1.12 |
Commencement Date of Works |
21 Jun
2011 |
Condition 2.11 |
Landscape
Plan (Revision B) |
20 Nov 2012 |
Condition
2.9 |
Noise
Management Plan (Revision B) |
13 Jan 2012 |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
3.1.8.
Summary of the current status on licences and/or permits on environmental
protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15
Nov 2010 |
Permit
issued |
Valid |
Notification
of Works Under APCO |
322293 |
07
Oct 2010 |
Notified |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0719-15 |
3 July 2015 |
06 Jul 2015 to 31 Dec 2015 |
Valid |
GW-RS0830-15 |
29 July 2014 |
30 Jul 2015 to 29 Jan 2016 |
Valid |
|
GW-RS1206-15 |
06 Nov 2015 |
12 Nov 2015 to |
Valid |
|
|
GW-RS1383-15 |
14 Dec 2015 |
19 Dec 2015 to 27 Mar 2016 |
Valid |
|
GW-RS1415-15 |
24 Dec 2015 |
01 Jan 2016 to 30 Jun 2016 |
Valid
|
Discharge
Licenses |
WT00012998-2012 |
25
May 2012 |
31
Jan 2016 |
Cancelled |
WT00013967-2012 |
17
Sep 2012 |
30
Sep 2017 |
Cancelled |
|
WT00014966-2013 |
08 Jan 2013 |
31 Jan 2018 |
Cancelled |
|
WT00020398-2014 |
21
Nov 2014 |
31
Jan 2016 |
Valid |
|
WT00020725-2015 |
14
Jan 2015 |
30
Jul 2017 |
Valid |
|
Registration
as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17
Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste Disposal Ordinance
(Land) |
Account No.: 7011587 |
11
Oct 2010 |
Account approved |
Valid |
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
EP Condition |
Submission |
Date
of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 6) |
19 May 2014 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.9.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0679-15 |
29 Jun
2015 |
01 Jul
2015 to 31 Dec 2015 |
Valid |
GW-RS893-15 |
17 Aug
2015 |
17 Aug
2015 to 16 Feb 2016 |
Valid |
|
GW-RS0990-15 |
10 Sep
2015 |
10 Sep
2015 to 09 Mar 2016 |
Valid |
|
GW-RS1160-15
|
26 Oct
2015 |
28 Oct
2015 to 25 Apr 2016 |
Valid |
|
|
GW-RS1303-15 |
26 Nov
2015 |
26 Nov
2015 to 25 May 2016 |
Valid |
Registration as a Chemical Waste
Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste
Disposal Ordinance (Disposal by Vessel) |
7011761 |
26 Jun 2015 |
17 Oct 2015 to 17 Jan 2016 |
Valid |
Water Discharge License (TS1) |
WT00008780-2011 |
24 Nov 2011 |
24 Nov 2011 to 31 Mar 2016 |
Valid |
Water Discharge License
(Discharge at CHT area) |
WT00019250-2014 |
6 Jun 2014 |
06 Jun 2014 to 31 May 2016 |
Valid |
Water Discharge License
(Discharge at TPCWAE) |
WT00018167-2014 |
17 Jan 2014 |
17 Jan 2014 to 31 Dec 2015 |
Valid |
Water Discharge License
(Discharge at TS4) |
WT00018542-2014 |
17 Mar 2014 |
17 Mar 2014 to 31 Jan 2016 |
Cancelled |
Water Discharge Licence
(Discharge at TPCWAW) |
WT00020601-2014 |
18 Mar 2015 |
18 Mar 2015 to 31 Mar 2017 |
Valid |
Table 3.9 Summary of submission status under
FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 Mar
2011 |
Amendment for Management
Organization of Main Construction Companies |
16 May
2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar
2011 |
Condition 2.8 |
Location Plan |
15 Mar
2011 |
Condition 2.9 |
Noise Management Plan |
6 May
2011 |
Condition
2.10 |
Landscape
Plan (Rev.3) |
30 Jan 2015 |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
3.1.10.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table
3.11.
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Superseded |
|
24 Nov 2015 |
N/A |
Valid |
||
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10
Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24
Mar 2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7012306 |
21
July 2011 |
N/A |
Valid |
Construction
Noise Permits (CNP) for non-piling equipment |
GW-RS0741-15 |
10 Jul 2015 |
23 Jul 2015 to 22 Jan 2016 |
Cancelled |
GW-RS0671-15 |
18 Jun 2015 |
20 Jun 2015 to 17 Dec 2015 |
Expired |
|
GW-RS0869-15 |
13 Aug 2015 |
15 Aug 2015 to 12 Feb 2016 |
Valid |
|
GW-RS0909-15 |
21 Aug
2015 |
21 Aug 2015
to 20 Feb 2016 |
Valid |
|
GW-RS1036-15 |
22 Sep 2015 |
24 Sep 2015 to 23 Mar 2016 |
Cancelled |
|
GW-RS1189-15 |
06 Nov 2015 |
09 Nov 2015 to 08 Dec 2015 |
Expired |
|
GW-RS1324-15 |
01 Dec 2015 |
08 Dec 2015 to 07 Jun 2016 |
Valid |
|
GW-RS1398-15 |
17-Jun-15 |
18 Dec 2015 to 17 Jun 2016 |
Valid |
|
Water
Discharge License |
WT00010093-2011 |
17 Aug 2012 |
30 Sep 2016 |
Valid |
WT00010865-2011 |
03 Nov 2011 |
30 Nov 2016 |
Cancelled |
|
Dumping
Permit (Approach Ramp) (Type 1 ¡V Open Sea Disposal) |
EP/MD/16-092 |
20 Nov
2015 |
15 May
2016 |
Valid |
Dumping
Permit (Approach Ramp) (Type 2 ¡V Confined Marine Disposal) |
EP/MD/16-093 |
20 Nov
2015 |
19 Dec
2015 |
Expired |
Table 3.11 Summary of submission status under
FEP-07/364/2009/D
EP Condition |
Submission |
Date of Submission |
Condition 2.13 |
Landscape Plan (Rev.3) |
19 August 2014 |
Condition 2.9 |
Noise Management Plan (Rev.4) |
2 Feb
2015 |
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West
3.1.11
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-09/364/2009/B for contract no.
HK/2012/08 showed in Table 3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
N/A |
Valid |
FEP-06/356/2009 |
5 March 2013 |
N/A |
Valid |
|
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
5213-134-C3790-01 |
8 Mar 2013 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0838-15 |
31 Jul 2015 |
03 Aug 2015 to 02 Feb 2016 |
Valid |
GW-RS0976-15 |
7 Sep 2015 |
23 Sep 2015 to 22 Mar 2016 |
Valid |
|
Water Discharge Licence |
WT00018223-2014 |
28 Jan 2014 |
31 Jan 2019 |
Cancelled |
WT00020594-2014 |
22 Dec 2014 |
31 Jan 2019 |
Valid |
Table
3.13 Summary
of submission status under FEP-09/364/2009/B
Submission |
Date of Submission |
|
Condition 2.9 |
Noise Management Plan (Rev.2) |
9 July 2013 |
Condition 2.14 |
Landscape Plan (Rev.4) |
24 August 2015 |
Contract
no. HY/2010/08 ¡VCentral ¡V Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8)
3.1.12
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-10/364/2009/B for contract no.
HK/2012/08 showed in Table 3.14 and Table 3.15.
Table
3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2010/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-10/364/2009/B |
26
Jul 2013 |
NA |
Valid |
FEP-07/356/2009 |
26
Jul 2013 |
NA |
Valid |
|
Notification of Works Under APCO |
357176 |
2013-04-02 |
NIL |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
2013-03-27 |
NIL |
Valid |
Billing Account under Waste Disposal
Ordinance |
7017170 |
2013-03-27 |
NIL |
Valid |
Water Discharge
License |
WT0001651-2013 |
2013-07-09 |
2018-07-28 |
Cancelled |
WT00020468-2014 |
2014-12-03 |
2018-07-31 |
Valid |
|
Construction
Noise Permit (CNP) for non-pilling works |
GW-RS0620-15 |
11 Jun 2015 |
11 Jun 2015 to 10 Dec 2015 |
Cancelled |
GW-RS0811-15 |
24 Jul 2015 |
29 Jul 2015 to 28 Jan 2016 |
Cancelled |
|
GW-RS0972-15 |
08 Sep 2015 |
09 Sep 2015 to 08 Mar 2016 |
Valid |
|
GW-RS0765-15 |
13 Jul 2015 |
13 July 2015 to 12 Jan 2016 |
Valid |
|
GW-RS0920-15 |
26 Aug 2015 |
28 Aug 2015 to 24 Feb 2016 |
Valid |
|
GW-RS0938-15 |
26 Aug 2015 |
28 Aug 2015 to 24 Feb 2016 |
Cancelled |
|
GW-RS1039-15 |
23 Sep 2015 |
23 Sep 2015 to 21 Mar 2016 |
Cancelled |
|
GW-RS1061-15 |
30 Sep 2015 |
02 Oct 2015 to 31 Mar 2016 |
Cancelled |
|
GW-RS1063-15 |
30 Sep 2015 |
02 Oct 2015 to 31 Mar 2016 |
Cancelled |
|
GW-RS1137-15 |
22 Oct 2015 |
22 Oct 2015 to 21 Apr 2016 |
Valid |
|
GW-RS1141-15 |
20 Oct 2015 |
22 Oct 2015 to 21 Apr 2016 |
Valid |
|
GW-RS1145-15 |
20 Oct 2015 |
22 Oct 2015 to 21 Apr 2016 |
Valid |
|
GW-RS1262-15 |
17 Nov 2015 |
18 Nov 2015 to 16 May 2016 |
Valid |
|
GW-RS1282-15 |
25 Nov 2015 |
25 Nov 2015 to 24 May 2016 |
Valid |
Table
3.15 Summary
of submission status under FEP-10/364/2009/B
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.3) |
03 January 2014 |
Condition 2.14 |
Landscape Plan (Rev.2) |
19 May 2014 |
Condition 2.16 |
Additional Mitigation Plan (Rev.2) |
18 February 2015 |
Contract
no. HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/B
3.1.13
The current status on licenses and/or permits on environmental
protection pertinent and submission under FEP-11/364/2009/B for contract no.
HY/2011/08 showed in Table 3.16 and Table 3.17.
Table
3.16 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2011/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
N/A |
Valid |
Notification of Works Under APCO |
LCAC-EN-LE-00017 |
7 Mar 2014 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-121-L2837-01 |
21 May 2014 |
N/A |
Valid |
5213-151-L2837-02 |
09 Oct 2015 |
N/A |
Registered |
|
5213-134-L2898-01 |
16 Nov 2015 |
N/A |
Registered |
|
Billing Account under Waste Disposal
Ordinance |
7019640 |
27 Mar
2014 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS-0678-15 |
19 June 2015 |
26 Jun 2015 to 25 Dec 2015 |
Expired |
GW-RS0738-15 |
06 July 2015 |
07 July 2015 to 31 Dec 2015 |
Valid |
|
GW-RS0758-15 |
07 July 2015 |
08 July 2015 to 31 Dec 2015 |
Valid |
|
GW-RS0856-15 |
10 Aug 2015 |
27 Aug 2015 to 26 Feb 2016 |
Valid |
|
GW-RS1235-15 |
12 Nov 2015 |
18 Nov 2015 to |
Valid |
|
GW-RS1423-15 |
24 Dec 2015 |
26 Dec 2015 to 31 May 2016 |
Valid |
|
GW-RS1426-15 |
29 Dec 2015 |
01 Jan 2016 to 30 Jun 2016 |
Valid |
|
GW-RS1433-15 |
29 Dec 2015 |
01 Jan 2016 to 30 Jun 2016 |
Valid |
|
Water Discharge Licence |
WT00020242-2014 |
04
Nov 2014 |
30
Nov 2019 |
Valid |
WT00020246-2015 |
15
Jul 2015 |
31
Jul 2019 |
Valid |
Table 3.17 Summary
of submission status under FEP-11/364/2009/B
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.2) |
27 Jan 2015 |
Condition 2.14 |
Landscape Plan (Rev.2) |
18 Feb 2015 |
Condition 2.13 |
Operational Air Quality Management Plan for West Ventilation Building
(Rev.0) |
25 Nov 2014 |
Condition 2.13 |
Operational Air Quality Management Plan for East Ventilation Building
and East Vent Shaft (Rev.0) |
18 Feb 2015 |
Noise
Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon-day
Gun Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
*M8 |
City Hall |
* Remark 1: Location ID has been updated from M7 to
M8 for City Hall
* Remark 2: M7e has become a reference station
starting from 7 Aug 2012
Real time Noise Monitoring
Stations
4.1.2.
The noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitfield Depot |
North
Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee
Mo Fan Memorial School |
Tin Hau |
RTN4 |
Causeway Bay
Community Centre |
Noise
Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P One set of measurements between 0700
and 1900 hours on normal weekdays.
4.1.5.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 - hours basis when noise
generating activities are underway:
¡P One set of measurements between 0700
and 1900 hours on normal weekdays.
¡P One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
¡P One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.6.
If construction works are extended to include
works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring
Equipment
4.1.7.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.8.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.9.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality
Monitoring Stations
4.2.1.
The air quality monitoring stations for the
Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Quality Monitoring
Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil
Street Site Office** |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
Causeway
Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: As
per the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB
site office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as ¡§Oil Street Site Office¡¨
in April 2013.
Remarks***: The
station ID and monitoring location was updated in December 2014 with respect to
monitoring station relocation.
Air QUALITY Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six days should be
undertaken when the highest dust impact occurs.
Sampling
Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
¡P 0.6 ¡V 1.7 m3 per minute
adjustable flow range;
¡P Equipped with a timing / control device
with +/- 5 minutes accuracy for 24 hours operation;
¡P Installed with elapsed-time meter with
+/- 2 minutes accuracy for 24 hours operation;
¡P Capable of providing a minimum exposed
area of 406 cm2;
¡P Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
¡P Equipped with a shelter to protect the
filter and sampler;
¡P Incorporated with an electronic mass
flow rate controller or other equivalent devices;
¡P Equipped with a flow recorder for
continuous monitoring;
¡P Provided with a peaked roof inlet;
¡P Incorporated with a manometer;
¡P Able to hold and seal the filter paper
to the sampler housing at horizontal position;
¡P Easily changeable filter; and
¡P Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory
Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8¡¨ x 10¡¨ shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24 hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of
equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure 2.1
and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange
Contract no.
HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no.
HY/2010/08 ¡V Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
Contract no. HK/2009/01
¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass at Wan
Chai East
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan
Chai West
Contract no.
HY/2011/08 ¡V Central - Wan Chai Bypass (CWB)¡V Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix 5.1.
5.1.1
Monitoring for report of review baseline
noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20
June 2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for
the noise calculation starting from January 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.1.2 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for
Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
*
Remark: M7e has become a reference station starting from 7 Aug 2012
5.1.3
No action or limit level exceedance was
recorded in this reporting month.
5.1.4
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02
¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East
(CWB Tunnel) under FEP-01/364/2009
5.1.5
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
noise monitoring stations are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract
no HK/2009/01
and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.6
Four limit level exceedances were recorded at M1a-
Harbour Road Sports Centre on 01, 08, 15 and 23 December 2015 in this reporting month.
5.1.7
Breaking works at Ex- Wan Chai Swimming Pool
(adjacent to Habour Road Sports Centre directly opposite to the monitoring
station) under non WDII-CWB Contractor was observed as the major noise
contribution during monitoring on 01, 08, 15 and 23 December 2015.
As such, the exceedance was considered as non-Project related.
5.1.8
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.1.9 The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.3 below.
Table 5.3
Noise Monitoring Stations
for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.10
No action or limit level exceedance was
recorded in this reporting month.
5.1.11
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.1.12 Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table 5.4
below.
Table 5.4 Noise
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.13
Two limit level
exceedances were recorded at monitoring station M6 - HK Baptist Church
Henrietta Secondary School on 11 and 16 December 2015 in this reporting month.
5.1.14
Major traffic noise observed during monitoring was considered as the
major noise contribution. As such, the limit level exceedances were concluded
as non-project related.
5.1.15
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 ¡V
Central-Wanchai Bypass ¡VWanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
5.1.16 The
commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02
September 2013. The proposed divisions of noise monitoring stations are
summarized in Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
5.1.17
No action or limit level exceedance was
recorded in this reporting month.
5.1.18
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡V Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.1.19 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2011/08 are summarized in Table 5.6 below:
Table 5.6
Noise Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station
starting from 7 Aug 2012
5.1.20
No action or limit level exceedance was
recorded in this reporting month.
5.1.21
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.2.1.
As confirmed by CWB RSS, the IECL parapet removal operations and
associated construction work was commenced in June 2013. Liaison was conducted with HK Baptist
Church Henrietta Secondary School, Po Leung Kuk Yu Lee Mo Fan Memorial School
and Causeway Bay Community Centre regarding the set up of RTN3 real time noise monitoring
station.
5.2.2.
Causeway Bay Community Centre has granted permission for set up on 21
Dec 2012 and station set up was performed on 27 Dec 2012. The baseline noise level of RTN4-
Causeway Bay Community Centre has adopted the results from the baseline noise
monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
5.2.3.
Real time noise monitoring at RTN4-Causeway Bay Community Centre was
commenced on 13 Jan 2013.
5.2.4.
Po Leung Kuk Yu Lee Mo Fan Memorial School granted permission for set up
on 4 Sep 2012 and station set up was performed on 14 Sep 2012. Real time noise
baseline capturing was conducted during time period without construction work
from 21 Sep 2012 to 04 Oct 2012.
5.2.5.
Real time noise monitoring at RTN3 ¡V Po Leung Kuk Yu Lee Mo Fan Memorial School was
commenced since 06 Oct 2012.
5.2.6.
Oil Street Community Liaison Centre was confirmed to be demolished in
mid-October by CWB RSS. This
presented a need for relocation of RTN2 ¡V Oil Street Community Liaison
Centre. After liaison with Hong
Kong Electric, permission was granted on 21 Sep 2012 for real time noise
monitoring set up at City Garden Electric Centre (RTN2a ¡V Electric Centre),
which is a representative of the noise sensitive receiver City Garden.
5.2.7.
RTN2 previously located at oil Street Community Liaison Centre was
relocated to Hong Kong Electric Centre on 5 Oct 2012, which is a representative
of the noise sensitive receiver City Garden. The baseline noise level of RTN2a
will adopt the results derived from the baseline noise monitoring conducted at
Electric Centre from 4 December 2009 to 17 December 2009.
5.2.8.
Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely
adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with
respect to the commencement of advance works for IEC parapet demolition.
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
5.2.9.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise monitoring
for major construction works under contract no. HY/2009/19 was commenced on 24
April 2011.
Table 5.7 Real
Time Noise
Monitoring Stations for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Electric Centre |
RTN3 |
North
Point |
Po Leung Kuk Yu Lee Mo Fan Memorial School |
RTN4 |
Tin
Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and graphical presentation during restrict
hours and night time period are for information only and noise during CNP
period shall be controlled under NCO.
5.2.10.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
5.2.11.
Limit level exceedance
was recorded at RTN2a-Electric Centre on 15 December 2015 during daytime in the
reporting month. On 15 December 2015, concreting was undertaken by Contract
HY/2009/19 while steel bar cutting works by saw cutter for Hong Kong Electric
Centre was conducted at the roof top by non-CWB Contractor immediately next to
the noise monitoring station and was considered as major noise contribution. As
such, the exceedance was considered as non-Project related.
5.2.12.
No limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during in the reporting month.
5.2.13.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre during daytime on 02 December 2015 in the
reporting month. On 02 December 2015, only steel mould dismantling works was
undertaken by Contract HY/2009/19 during monitoring while scaffold dismantling and
manual handling of material was observed undertaken by non-CWB Contractor at
Causeway Bay Community Centre in close proximity to the monitoring station and
was considered as the major noise contribution. As such, the exceedances were
considered as non-Project related.
5.2.14.
Real time noise monitoring results measured
in this reporting period are reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 5.4.
Contract no. HY/2011/08 ¡V Central - Wan Chai
Bypass (CWB) ¡V Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning
5.2.15.
The proposed division of noise monitoring
stations are summarized in Table 5.8 below. Real time noise
monitoring for major construction works under contract no. HY/2011/08 was
commenced on 19 March 2015.
Table 5.8 Real
Time Noise
Monitoring Stations for Contract
no. HY/2011/08
Location
ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section
Whitfield Depot |
* Real time noise monitoring results and
graphical presentation during restrict hours and night time period are for
information only and noise during CNP period shall be controlled under NCO.
5.2.16.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
Contract no. HY/2009/18 ¡V
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.3.1
Air quality monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.9 below.
Table
5.9 Air Quality Monitoring Stations for Contract
no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
5.3.2
No exceedance was recorded in the reporting
month.
5.3.3
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
5.3.4
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality
monitoring stations are summarized in Table 5.10 below.
Table 5.10 Air Quality Monitoring Station for Contract
no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.5
No exceedance was recorded in the reporting
month.
5.3.6
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.7
The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
air quality monitoring stations are summarized in Table 5.11
below.
Table 5.11 Air Quality Monitoring Station for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.8
No exceedance was recorded in the reporting
month.
5.3.9
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.3.10
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air
quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.12 below.
Table 5.12
Air
Quality Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.11
No exceedance was recorded in the reporting
month.
5.3.12
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.3.13
The proposed division of air quality monitoring
stations are summarized in Table 5.13 below. Air quality monitoring
for the tunnel works under contract no. HY/2009/19 was commenced on 26 April
2011.
Table 5.13 Air Quality
Monitoring
Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
5.3.14
No exceedance was recorded in the reporting
month.
5.3.15
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08- Wan Chai Development Phase
II ¡V Central-Wan Chai Bypass at Wan Chai West
5.3.16
The commencement of construction works for
Contract no. HK/2012/08 under FEP-09/364/2009/C was on May 2014. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.14 below.
Table 5.14
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.17
No exceedance was recorded in the reporting
month.
5.3.18
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2010/08 ¡V
Central-Wanchai Bypass ¡VWanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
5.3.19
The commencement of construction works for
Contract no. HY/2010/08 under FEP-09/364/2009/B was on July 2014. Air quality
monitoring was commenced on 14 July 2011. The
proposed division of air quality monitoring stations are summarized in Table
5.15 below.
Table 5.15
Air
Quality Monitoring Station for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.20
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡V Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.3.21
Air quality monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.16 below.
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
5.3.22
No exceedance was recorded in the reporting
month.
5.3.23
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
5.4.1.
Inert C&D wastes and non-inert C&D wastes were disposed in this
reporting month. Details of the waste flow table are summarized in
Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed, m3 |
Nil |
106130.58 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
6472.5 |
97630.03 |
N/A |
Non-inert C&D materials disposed, m3 |
34.05 |
3728.2 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
42950 |
1065766 |
N/A |
Chemical waste disposed, kg |
20 |
10400 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal) , m3 |
Nil |
10375 |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
Nil |
16261 |
East of Cha Chau South Brothers |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.4.2.
Inert C&D & non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
4 |
456338.412 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
Nil |
46520 |
N/A |
Non-inert C&D materials disposed, m3 |
83 |
2253.317 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
Nil |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
18253 |
SENT Landfill |
Marine Sediment (Type 1 ¡V Open Sea Disposal)
, m3 |
Nil |
27889 |
South Cheung Chau |
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
5.4.3.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
2291.41 |
167085.381 |
||
Nil |
58787.05 |
||
55.91 |
3780.316 |
||
2.16 |
878.37 |
||
Nil |
4440 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.4.
Inert & Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
13568 33.4 |
618555.47 251284.7 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled, m3 |
Nil |
358660.77 |
HY/2009/11 ex-PCWA TS4 /TS2 WDII Lun Ku Tan WENT |
Non-inert C&D
materials disposed, m3 |
171.3 |
3585.13 |
SENT Landfill |
Non-inert C&D
materials recycled, m3 |
Nil |
5496446.2 |
Xun Xiang Metalware
Skylight Recycle (paper) |
Chemical waste disposed, kg |
Nil |
22755 |
Dunwell Group |
Marine Sediment
(Type1-Open Sea Disposal (Dedicate Sites) &Type 2 ¡V Confined Marine
Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
5.4.5.
Inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21.
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed, m3 |
1570.56 |
631820.51 |
N/A |
Inert
C&D materials recycled, m3 |
Nil |
81822.39 |
N/A |
Non-inert
C&D materials disposed, m3 |
102.07 |
4138.62 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
15.22 |
482.63 |
N/A |
Chemical
waste disposed, kg |
Nil |
9.69 |
N/A |
Marine
Sediment (Tunnel) (Type-1 Open Sea Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine
Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 ¡V
Confined Marine Disposal), m3 |
Nil |
30751 |
East of Sha Chau |
Contract no. HK/2012/08 Wan Chai
Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
5.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.22.
Table 5.22 Details of Waste
Disposal for Contract no. HK/2012/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
8694 |
114114 |
TKO 137 |
Inert
C&D materials recycled, m3 |
581 |
36107 |
N/A |
Non-inert
C&D materials disposed, m3 |
85 |
940 |
SENT |
Non-inert
C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical
waste disposed, kg |
Nil |
Nil |
N/A |
Marine
sediment (Type 1) disposal, m3 |
Nil |
3145 |
South of Cheung Chau / East of Sha Chau / South
of The Brothers |
Contract no. HY/2010/08
Central
¡V Wan Chai Bypass (CWB) ¡V Tunnel (Slip Road 8) under FEP-10/364/2009/B
5.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.23.
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
21,511 21 |
396,504 410 |
TM 38 TKO 137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
73 |
1355 |
SENT |
Non-inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste disposed, kg |
Nil |
979 |
N/A |
Table 5.23 Details of Waste Disposal for
Contract no. HY/2010/08
Remarks: The
cumulative quantity for inert C&D materials disposed and the inert C&D
material recycled under Contract HY/2010/08 subject to further clarified upon RSS
confirmation.
Contract no. HY/2011/08
Central
¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009B
5.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.24.
Table 5.24 Details of Waste Disposal for
Contract no. HY/2011/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
75.6 |
331.87 |
CWPF & TKO137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
52.51 |
488.84 |
SENT |
Non-inert C&D materials recycled, ton |
Nil |
31.72 |
N/A |
Chemical waste disposed, kg |
Nil |
3800 |
N/A |
6.0.1.
The Event Action Plan for construction noise,
air qualities are presented in Appendix 6.1.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
6.1.1. No exceedance
was recorded in the reporting month.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention Exhibition Centre
¡V Tunnel Works under FEP-02/364/2009
6.1.2.
Four limit level exceedances were recorded at M1a- Harbour Road Sports
Centre on 01, 08, 15 and 23 December 2015 in this reporting month.
6.1.3.
Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road
Sports Centre directly opposite to the monitoring station) under non WDII-CWB
Contractor was observed as the major noise contribution during monitoring on 01,
08, 15 and 23 December 2015. As
such, the exceedance was considered as non-Project related.
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.4.
Four limit level exceedances were recorded at M1a- Harbour Road Sports
Centre on 01, 08, 15 and 23 December 2015 in this reporting month.
6.1.5.
Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road
Sports Centre directly opposite to the monitoring station) under non WDII-CWB
Contractor was observed as the major noise contribution during monitoring on 01,
08, 15 and 23 December 2015. As
such, the exceedance was considered as non-Project related.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
6.1.6. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.7. Two limit level
exceedances were recorded at M6 ¡V HK Baptist Church Henrietta
Secondary School on 11 and 16 December 2015.
6.1.8. Investigations
found that on 11 and 16 December 2015, traffic noise were major contribution in
the noise monitoring and exceedances were not related to the Project.
Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.1.9. No exceedance
was recorded in the reporting month.
Contract no. HY/2011/08 Central ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
6.1.10. No exceedance
was recorded in the reporting month.
Real Time Noise Monitoring
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.11. No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
6.1.12. Limit level exceedance
was recorded at RTN2a-Electric Centre on 15 December 2015 during daytime in the
reporting month. On 15 December 2015, concreting was undertaken by Contract
HY/2009/19 while steel bar cutting works by saw cutter for Hong Kong Electric
Centre was conducted at the roof top by non-CWB Contractor immediately next to
the noise monitoring station and was considered as major noise contribution. As
such, the exceedance was considered as non-Project related.
6.1.13. No limit level
exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School during in the
reporting month.
6.1.14. Limit level
exceedances were recorded at RTN4-Causeway Bay Community Centre during daytime
on 02 December 2015 in the reporting month. On 02 December 2015, only steel mould
dismantling works was undertaken by Contract HY/2009/19 during monitoring while
scaffold dismantling and manual handling of material was observed undertaken by
non-CWB Contractor at Causeway Bay Community Centre in close proximity to the
monitoring station and was considered as the major noise contribution. As such,
the exceedances were considered as non-Project related.
Contract no. HY/2011/08
Central ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
6.1.15. No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
6.2.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
6.2.2.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.2.3.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
6.2.4.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.2.5.
No exceedance was recorded in the reporting
month.
Contract no. HK/2012/08 Wan Chai Development Phase
II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
6.2.6.
No exceedance was recorded in the reporting
month.
Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.2.7.
No exceedance was recorded in the reporting
month.
Contract no. HY/2011/08
Central
¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009B
6.2.1
No exceedance was recorded in the reporting
month.
6.3.1.
There was no non-compliance from the site
audits and monitoring in the reporting period. The observations and
recommendations made in each individual site audit session were presented in
Section 8.
6.4.1
There was no particular action taken since no
non-compliance was recorded from the site audits and monitoring in the
reporting period.
7.0.1.
According to Condition 3.4 of the
EP-364/2009/C, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Final
EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
the major construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water
quality monitoring was completed in October 2011. As such, it is considered that there
were no cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area
include caisson seawall installation, ELS works, road works and drainage works
and Road P1 pedestrian road reinstatement were performed in December 2015
reporting month. As no project related exceedance were recorded
during the reporting period, cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was considered as insignificant.
7.0.4. According to the construction programme of Wan Chai Development Phase
II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the
major construction activities under Wan Chai Development Phase II were
tunnel works, ELS works and road works at Wan Chai East and caisson
installation, D-wall construction and ELS works at Wan Chai West. The
major construction activities under Central-Wan Chai Bypass and Island Eastern
Corridor Link Projects were bridge construction and road works at Central
Interchange, ELS works at Ex-PCWAW, ELS works and retaining wall construction at
Victoria Park; D- wall construction, ELS works and tunnel works at TS3; IEC removal
works and tunnel works at North Point area in the reporting month. In addition,
other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island
Eastern Corridor Link projects was observed undertaken at Wan Chai North area.
7.0.5.
No significant air quality impact from
construction activities was anticipated in the reporting month. Besides, no project
related exceedance was recorded during the air quality and noise environmental
monitoring events in the reporting month. Thus, it is evaluated that the
cumulative construction impact from the concurrent projects including Central
Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was
insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HY/2009/15, HY/2009/18,
HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02, HY/2010/08 and HY/2011/08. No
non-conformance was identified during the site audits. The Contractors rectified major
observations and recommendations made during the audit sessions. No
non-conformance was identified during the site inspections.
8.0.2.
Four site inspections for Contract no.
HY/2009/15 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
151209_1 |
9-Dec-2015 |
Review the
conditioning and coagulant dosage applied to ensure no turbid discharge (EX-PCWAW) |
No further turbid
discharge was observed |
Completed as observed
on 15 December 2015 |
151215_1 |
15-Dec-2015 |
Discharge point of
washing sink shall be connected to waste water treatment plant (EX-PCWA East) |
Discharge point of washing
sink has been connected to collection pit (EX-PCWA East) |
Completed as observed
on 22 December 2015 |
8.0.3.
Five site inspections for Contract no.
HY/2009/18 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.2.
Table 8.2 Summary of Environmental Inspections for
Contract no. HY/2009/18
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
151210_2 |
10-Dec-15 |
Idle stockpile shall
be covered properly to prevent dust emission (Man Chiu Street) |
Covering and watering
has been provided to stockpile |
Completion as
observed on 17 Dec 2015 |
8.0.4.
Four site inspections for Contract no.
HY/2009/19 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.3.
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
151202_1 |
02-Dec- 2015 |
Noise barriers
provided to construction of substructure works shall installed according to
EP condition (Portion III) |
No further
construction of substructure was observed and the barrier was installed as
per requirement |
Completion as
observed on 21 December 2015 |
8.0.5.
Four site inspections for Contract no.
HK/2009/01 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.4
Table 8.4 Summary of Environmental Inspections for
Contract no. HK/2009/01
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
151202_01 |
2-Dec-15 |
Drip tray shall be
provided for oil container at slip road 3 |
Oil container has
been removed and disposed. |
Completion as
observed on 9 December 2015 |
151209_01 |
9/12/2015 |
Drip tray shall be
provided to oil container (Stage 1) |
Oil container has
been removed and disposed. |
Completion as
observed on 17 December 2015 |
8.0.6.
Four site inspections for Contract no.
HK/2009/02 was carried out during this reporting period. No observation was
found in the reporting month. The results of these inspections and outcomes are
summarized in Table 8.5.
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
151203_01 |
3-Dec-15 |
Hole of drip tray
under mechanical pump shall be covered at WCR3 |
The hole of drip tray
has been covered at WCR3. |
Completion as
observed on 10 December 2015. |
151203_02 |
3-Dec-15 |
The gap of silt
curtain at RW21-P789 shall be minimized to properly maintain the silt curtain
condition. |
Silt curtain at
RW21-P789 has deployed to seabed level. |
Completion as
observed on 16 December 2015. |
151203_03 |
3-Dec-15 |
Silt above the
seawall block shall be cleaned to prevent any surface runoff during the
coming rainstorm at WCR3. |
Silt above the
seawall block was cleaned at WCR3. |
Completion as
observed on 10 December 2015. |
8.0.7.
Four site inspection for Contract no.
HK/2012/08 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.6
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
151208_01 |
8-Dec-15 |
Floating refuse
shall be collected at Zone A2 area. |
Floating refuse was
cleared at Zone A2. |
Completion as observed
on 15 December 2015 |
151208_02 |
8-Dec-15 |
Silt curtain at the
opening of water channel shall be repaired and properly maintain. |
Silt curtain was
repaired and properly deployed. |
Completion as
observed on 15 December 2015 |
151222_01 |
22-Dec-15 |
Muddy effluent at
site exit and public road shall be cleaned regularly in an orderly manner. |
The site exit and
public road were cleaned properly. |
Completion as
observed on 29 December 2015 |
151222_02 |
22-Dec-15 |
Direct discharge
from boxes was observed at water channel, contaminated effluent shall be
collected in proper manner and treated before discharge. |
Discharge was
stopped and no further discharge was observed. |
Completion as
observed on 22 December 2015 |
Item |
Date |
Observations |
Action taken by Contractor |
Completion date |
151202_1 |
2-Dec-15 |
Piping with ide ends
shall be removed to avoid potential discharge (TS3) |
Idle pipes were
removed |
Completion as
observed on 3 December 2015 |
151202_2 |
2-Dec-15 |
The contractor shall
critically review the storage holding tank to avoid overflow to nearby water
(TS3) |
The holding tank of
concern was abandon from used. |
Completion as
observed on 9 December 2015 |
151202_3 |
2-Dec-15 |
Review the dosage and
operation of waste water treatment plant to avoid turbid discharge (TS3) |
No further turbid
discharge was observed |
Completion as
observed on 3 December 2015 |
151202_4 |
2-Dec-15 |
Effluent pipe from
the desilting compartment of the waste water treatment plant shall be
properly connected to a collection pit or disconnected (TS3) |
The piping from the
desilting compartment was stored properly to avoid accidental discharge. |
Completion as
observed on 14 December 2015 |
151202_5 |
2-Dec-15 |
Clean the leaked oil
as chemical waste (TS3) |
Leaked oil has been
cleared |
Completion as
observed on 3 December 2015 |
151203_1 |
3-Dec-15 |
Damaged barrier
around site boundary shall be repaired (Victoria Park) |
Damaged barrier was
repaired |
Completion as
observed on 9 December 2015 |
151203_2 |
3-Dec-15 |
Drip tray shall be
provided for chemical containers |
The chemical container
was removed |
Completion as
observed on 9 December 2015 |
151209_1 |
9-Dec-15 |
Clear the soil
deposit at the boundary of site location to prevent direct wash off of
contaminated effluent (TS3 North) |
Mud residue deposited
has been cleared |
Completion as observed
on 16 December 2015 |
151209_2 |
9-Dec-15 |
Tarpaulin sheet shall
be provided/reinstated after repositioning of barge prior to resumption of
excavated material transfer to prevent drop off |
The tarpaulin
sheeting was rearranged at proper position for excavated material transfer |
Completion as
observed on 11 December 2015 |
151211_1 |
11-Dec-15 |
Contractor was
advised to clean the mud deposit within waste water treatment plant before
resumption of plant operation to avoid discharge contamination (Victoria
Park) |
The mud residue
within the treatment unit was cleared |
Completion as
observed on 14 December 2015 |
8.0.8.
Eight site inspections for Contract no.
HY/2010/08 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.7
Table 8.7 Summary of Environmental Inspections for Contract no. HY/2010/08
151211_2 |
11-Dec-15 |
Review
the adequacy of the barrier in height to ensure sufficient height of 2.4m
(Victoria Park) |
The
condition of the barrier was improve. |
Completion
as observed on 14 December 2015 |
151211_3 |
11-Dec-15 |
Clear
the floating scum around works boundary (TS3) |
Floating
refuse have been cleared |
Completion
as observed on 14 December 2015 |
151211_4 |
11-Dec-15 |
Provide
drip tray for chemical container (Victoria Park Road) |
The
chemical container was removed |
Completion
as observed on 14 December 2015 |
151214_1 |
14-Dec-15 |
Provide
watering to breaking works (TS3) |
No
further concerned breaking works was observed |
Completion
as observed on 16 December 2015 |
151216_1 |
16-Dec-15 |
Critical
review the capacity and operation of waste water treatment plant and avoid
potential turbid discharge (TS3 West) |
No
further turbid discharge was observed |
Completion
as observed on 22 December 2015 |
151216_2 |
16-Dec-15 |
Drip
tray shall be provided to oil containers (TS3) |
Oil
container was removed |
Completion
as observed on 31 December 2015 |
151224_1 |
24-Dec-15 |
Fine
particular was observed at the outlet tank of the wastewater treatment
system. The contractor was advised to review the operation condition and
dosage and recirculate for treatment before discharge (TS3 West) |
No
further fine particulates were observed |
Completion
as observed on 29 December 2015 |
151224_2 |
24-Dec-15 |
Clean
the mud/silt deposition to ensure proper settling prior to resuming the plant
operation (Victoria Park) |
The
mud deposition was cleared |
Completion
as observed on 29 December 2015 |
8.0.9.
Four site inspections for Contract no. HY/2011/08
were carried out during this reporting period. No observation was found in the
reporting month.
9.0.1.
Two environmental complaints were received in the reporting month.
9.0.2.
First public complaint regarding construction dust impact referred by
EPD was received by ET on 04 December 2015 (EPD Ref: H04/RS/00028924-15). The
complainant reported that excessive construction dust was generated from the
construction site near Two International Finance Centre at Finance Street,
Central
ET confirmed with the Resident Site Staff
that bridge works and drains/ sewers construction at the concerned location was
undertaken by Contract HY/2009/18 on 12 November 2015. A stockpile which would be reused for
backfilling was stored at the concerned location by Contract HY/2009/18 on 12
November 2015.
Mitigation measures implemented by the
Contractor for the above construction works including covering of idled portion
of stockpile and dampening of the exposed stockpile was implemented for the
stockpile at the concerned location.
According to relevant site records
confirmed by RSS, bridge works and drains/ sewers construction at the concerned
location was undertaken by Contractor of HY/2009/18 on 12 November 2015 and a
stockpile which would be reused for backfilling was stored at the concerned
location. Mitigation measures including covering of idled portion of stockpile
and dampening of the exposed stockpile was implemented for the stockpile at the
concerned location.
In view of the public concern on
potential dust impact at the concerned location, the Contractor of HY/2009/18
rearranged the works sequence and placed concrete blocks at the bridge
retaining wall to allow for early commencement of backfilling on 19 November
2015 to minimize the size of the stockpile at an earlier stage. Additional
water sprinklers were installed on 27 November 2015 to further enhance the
dampening of the stockpile surface during excavation.
Follow-up inspection was conducted
during weekly environmental inspection on 10 December 2015 and mitigation
measures including covering of stockpile stored at the concerned location was
implemented while it was observed that stockpiles stored near Man Chiu Street
was not properly covered. The Contractor of HY/2009/18 was advised to promptly
provide covering to all idled stockpile stored on site and the Contractor was
reminded to enhance the watering during excavated material handling near the
concerned location. Further follow up inspection was conducted on 17 December
2015 and mitigation measures including covering and watering for idle stockpile
and material handling were implemented.
9.0.3.
Second public complaint regarding noise impact referred by RSS was
received by ET on 16 December 2015 (ICC Case Ref.: 2-1656689815 dated 14
December 2015). The complainant reported that incessant noise emanating from
the construction site of the Island Eastern Corridor Link that forms part of
the Central-Wanchai Bypass Project.
Over the past couple of weeks, there
have been loud mechanical pounding at the construction site over the reclaimed
area between Blocks 10 and 11 of City Garden. As can be seen, machines have
been breaking open the concrete paved on top of the reclaimed area. Work often
starts well before 9am on weekdays and, barring a brief period of lull during
lunch hours, would often continue unabated until after 5pm. Although I note
that certain noise reduction measures have been put into place (e.g. the
erection of flimsy noise barriers around the work area), the noise created is
still enormous, and this has become a significant nuisance for residents living
in nearby blocks of our estate, especially children and the elderly who have to
stay at home for longer hours.
ET confirmed with the Resident Site
Staff that concreting breaking works was carried out with one breaker on 7, 9,
11, 12 and 14 December 2015 and the breaking works at the concerned location
were completed on 14 December 2015 morning. Noise mitigation measures including
temporary noise barriers near the point of breaking and covering the breaker
with acoustic mat were provided during the concerned concrete breaking works.
According to information confirmed by
RSS, concreting breaking works was carried out by one excavator mounted breaker
on 7, 9, 11, 12 and 14 December 2015 and the concerned breaking works outside City
Garden Block 10 and Block 11 was completed on 14 December 2015 morning. Noise
mitigation measures including temporary noise barriers near the point of
breaking and covering the breaker with acoustic mat were provided during the
concerned concrete breaking works. Based on the further review on the record of
the environmental inspection conducted on 09 December 2015, the Contractor of
HY/2009/19 was reminded to temporary noise barrier provided for the pile cap demolition
shall follow the Environmental Permit EP-364/2009/D requirement.
Follow up inspection was conducted
during weekly environmental inspection on 17 December 2015, the concerned
breaking works opposite to City Garden Block 10 and Block 11 was observed
completed while the Contractor was reminded that the remaining section of
temporary noise barrier in accordance with the latest Environmental Permit
EP-364/2009/D shall be completed on site as soon as possible. According to the
information provided by RSS, the temporary noise barrier in accordance with the
Environmental Permit requirement opposite to City Garden was substantially
completed on 21 December 2015. In view of the public concern, the Contractor
was suggested to consider to review the works duration at daytime and conduct
other future breaking works around the concerned location intermittently to
minimize the potential noise nuisance caused to the surroundings.
9.0.4.
Referring to the complaint case regarding the illegal disposal of
construction waste referred by EPD was received by ET on 17 November 2015, the updated
2nd and 3rd interim investigation report were submitted
to the EPD on 17 December 2015 and 31 December 2015 respectively. In response
to the complaint concern, additional water quality monitoring and additional
site inspections have been conducted by the ET and the investigation findings
were included in the interim investigation reports separately submitted to the
EPD. In addition, the ET and IEC have conducted checking on the waste disposal
records and site construction records with the CWB RSS team to confirm the key
construction activities during the concerned period and the quantities of inert
C&D material disposed. Upon further review on relevant records and follow
up inspections on the implementation of site measures, the final investigation
would be issued.
9.0.5.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.6. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on
Complaints
Reporting Period |
No. of Complaints |
December 2015 |
2 |
September 2010 ¡V November 2015 |
51 |
Total |
53 |
Table
9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be commenced in
Coming Reporting Month
Contract No. |
Key Construction
Works |
Recommended Mitigation Measures |
HY/2009/15 |
¡P
Remedial works at Mined Tunnel ¡P
Excavation and RC structure works at TPCWAW ¡P
Remaining works inside tunnel at TS4 and TPCWAE ¡P
Removal of standby Dewatering System and monitoring instrument along
Hung Hing road |
¡P
Dust control during dust generating activities ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the nearby water. |
HY/2009/18 |
¡P
Drainage works ¡P
Road works ¡P
Bridges construction |
¡P
Dust control during dust generating activities ¡P
Provide protection works to ensure no runoff out of site area or
direct discharge into public drainage system. |
HY/2009/19 |
¡P
Pier construction for IEC ¡P
Construction of EVB ¡P
Column modification at F1 to F8 ¡P
Watson Road laying of new water pipe ¡P
Oil Street drainage works ¡P
Excavation / Construction of retaining wall/Approach Ramp/ADB ¡P
Bridge segment erections ¡P
Pre-bored H-pile for Approach Ramp ¡P
Hing Fat Street modification works ¡P
Bridge TA2 demolition ¡P
Abutment D12 construction |
¡P
Noise level shall be controlled by reducing the breaking operation
rate. ¡P
Noise barrier shall be implemented ¡P
Dust control during dust generating works ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. |
HK/2009/01 |
¡P
Stage 1 ,2 & 3 Backfilling works at CWB Tunnel top slab ¡P
Stage 2 Construction of slip road 3 ¡P
Stage 3 RC structure for CWB Tunnel Bay 18 to 20 ¡P
Removal of abandoned cooling main (P7/P9) at Convention Avenue ¡P
Reinstatement of outfall ¡P
Reinstatement of triangular planter at Fenwick Pier Street ¡P
Roadworks /drains for Expo Drive East ¡P
Stage 4 ELS works |
¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. ¡P
Dust control during dust generating works |
HK/2009/02 |
¡P
Completion of road side barriers ¡P
Backfilling works ¡P
Cutting the top part of diaphragm wall ¡P
Strut layer S6 lateral support installation ¡P
Breaking through bulkhead wall BW3 ¡P
Pouring blinding layer concrete ¡P
Tunnel construction at west side ¡P
Waterproofing layer application ¡P
Ground investigation works for bored piles and diaphragm wall ¡P
Bored pile construction ¡P
Pre-treatment works and guide wall construction for diaphragm wall ¡P
Diaphragm wall construction ¡P
Extraction of the temporary sheetpile seawall and removal of the
temporary seawall blocks near the interface between Portion 2 and Portion 5 |
¡P
Dust control during dust generating works ¡P
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |
HK/2012/08 |
¡P
Diaphragm wall construction ¡P
Grouting ¡P
Construction of MVB ¡P
Pre-bored H-pile construction ¡P
Construction of concrete plug ¡P
Excavation and lateral support installation |
¡P
Dust control during dust generating works ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system. |
HY/2010/08 |
¡P
Tree protection works next to existing BGO, ¡P
Drainage improvement works, ¡P
Sheet piling works, ¡P
Excavation and Lateral Support for U-structure, ¡P
Pipe piling & grouting works, ¡P
Utility diversion works, ¡P
Retaining wall works ¡P
ELS works, ¡P
Diaphragm Wall, Barrette construction and king post installation
works ¡P
D-wall drill cutting works ¡P
Construction works for subway extension |
¡P
Dust control during dust generating works ¡P
Appropriate measures should be taken to ensure adequate protections
are provided for trees being transplanted and retained on site. ¡P
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |
HY/2011/08 |
¡P
West Ventilation Building Construction ¡P
East Ventilation Shaft Construction ¡P
Tunnel Thermal Barrier Construction |
¡P
Dust control during dust generating works |
10.0.3.
The construction works of Contract no.
04/HY/2006 ¡V Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
10.0.4.
The construction works of Contract no.
HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was
completed, and the FEP was surrendered by the Contractor and found in order by
EPD on 25 April 2013.
10.0.5.
The construction works of Contract HK/2010/06
was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3
October 2014.