Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-364/2009/D,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B

 

Monthly Environmental Monitoring & Audit Report

 

- December 2015 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and                                            

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

 

14 January 2016


Table of contents         

 

EXECUTIVE SUMMARY.. 4

1.         Introduction.. 14

1.1        Scope of the Report 15

1.2        Structure of the Report 15

 

2.         Project Background.. 17

2.1        Background. 17

2.2        Scope of the Project and Site Description. 17

2.3        Division of the Project Responsibility. 18

2.4        Project Organization and Contact Personnel 19

 

3.         status of regulatory compliance.. 24

3.1        Status of Environmental Licensing and Permitting under the Project 26

 

4.          Monitoring Requirements.. 41

4.1        Noise Monitoring. 41

4.2        Air Quality Monitoring. 43

 

5.         Monitoring Results.. 45

5.1        Noise Monitoring Results. 46

5.2        Real Time Noise Monitoring Results. 49

5.3        Air Quality Monitoring Results. 52

5.4       Waste Monitoring Results. 56

 

6.         Compliance Audit.. 62

6.1        Noise Monitoring. 62

6.2        Air Quality Monitoring. 64

6.3        Review of the Reasons for and the Implications of Non-compliance. 65

6.4        Summary of action taken in the event of and follow-up on non-compliance. 65

 

7.         Cumulative Construction Impact due to the Concurrent Projects.. 66

8.         Enviromental site audit.. 67

9.         Complaints, Notification of Summons and Prosecution.. 72

10.       Conclusion.. 75


lIST OF TABLES

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.3      Summary of submission status under FEP-02/364/2009

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.5      Summary of submission status under FEP-01/364/2009

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.7      Summary of submission status under FEP-05/364/2009/A

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.9      Summary of submission status under FEP-06/364/2009/A

Table 3.10    Cumulative Summary of Valid License and Permits under Contract no. HY/2009/19

Table 3.11   Summary of submission status under FEP-07/364/2009/D

Table 3.12    Cumulative Summary of Valid License and Permits under Contract no. HK/2012/08

Table 3.13    Summary of submission status under FEP-09/364/2009/B

Table 3.14    Cumulative Summary of Valid License and Permits under Contract no. HY/2010/08

Table 3.15    Summary of submission status under FEP-10/364/2009/B

Table 3.16    Cumulative Summary of Valid License and Permits under Contract no. HY/2011/08

Table 3.17    Summary of submission status under FEP-11/364/2009/B

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Quality Monitoring Stations

Table 5.1      Noise Monitoring Stations for Contract no. HY/2009/18

Table 5.2      Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.3      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.5      Noise Monitoring Stations for Contract no. HY/2010/08

Table 5.6      Noise Monitoring Stations for Contract no. HY/2011/08

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.8      Real Time Noise Monitoring Stations for Contract no. HY/2011/08

Table 5.9      Air Quality Monitoring Station for Contract no. HY/2009/18

Table 5.10    Air Quality Monitoring Station for Contract no. HK/2009/01

Table 5.11    Air Quality Monitoring Station for Contract no. HK/2009/02

Table 5.12    Air Quality Monitoring Stations for Contract no. HY/2009/15

Table 5.13    Air Quality Monitoring Station for Contract no. HY/2009/19

Table 5.14    Air Quality Monitoring Station for Contract no. HK/2012/08

Table 5.15    Air Quality Monitoring Stations for Contract no. HY/2010/08

Table 5.16    Air Quality Monitoring Stations for Contract no. HY/2011/08

Table 5.17    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.18    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.20    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.21    Details of Waste Disposal for Contract no. HY/2009/19

Table 5.22    Details of Waste Disposal for Contract no. HK/2012/08

Table 5.23    Details of Waste Disposal for Contract no. HY/2010/08

Table 5.24    Details of Waste Disposal for Contract no. HY/2011/08

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.2      Summary of Environmental Inspections for Contract no. HY/2009/18

Table 8.4      Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.5      Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.6      Summary of Environmental Inspections for Contract no. HK/2012/08

Table 8.7      Summary of Environmental Inspections for Contract no. HY/2010/08

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

LIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.2    Copies of Calibration Certificates

Appendix 5.1    Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2    Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1    Event Action Plans

Appendix 6.2    Notification of Exceedance

Appendix 9.1    Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V December 2015 specific for Environmental Permit no. EP-364/2009/D, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 ¡V Wan Chai Development Phase II and Central Wanchai Bypass ¡V Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period of 28 November 2015 to 26 December 2015.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

¡P          Drainage works

¡P          Road works

¡P          Bridges construction

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

¡P          Stage 1 & 2 Backfilling works at CWB Tunnel top slab

¡P          Construction of slip road 2 and slip road 3

¡P          Stage 3 RC structure for CWB Tunnel Bay 18 to 20

¡P          Removal of abandoned cooling main (P7/P9) at Convention Avenue

¡P          Reinstatement of outfall was

¡P          Reinstatement of triangular planter at Fenwick Pier Street

¡P          Roadworks /drains for Expo Drive East

¡P          Stage 4 ELS works

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009                                     

¡P          Removal of stockpile of material, site clearance works at Tunnel Portion 1.

¡P          Construction of road side barriers

¡P          Backfilling works and access shaft construction

¡P          Construction of road side barriers

¡P           Struts installation for layer S6

¡P          Excavation for layer S6 and formation level

¡P          Construction of blinding layer

¡P          Breaking through bulkhead wall BW3

¡P          Ground investigation works

¡P          Bored pile construction

¡P          Extraction of the temporary sheet pile seawall and removal of the temporary seawall blocks near the interface between Portion 2 and Portion 5.

¡P          Setting up of silo tanks, pre-treatment works for diaphragm wall construction

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

¡P          Construction roadside barrier at Mined Tunnel

¡P          Rock excavation at TPCWAW

¡P          Demolition of bulkhead wall between TPCWAE and TPCWAW

¡P          Construction RC structure at TPCWAW

¡P          Remaining works inside tunnel at TS4 and TPCWAE

¡P          Removal of standby Dewatering System and monitoring instrument along Hung Hing road

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

¡P          Pier construction for IEC

¡P          Construction of EVB

¡P          Column modification at F1 to F8

¡P          Bridge E deck construction

¡P          Watson Road laying of new water pipe

¡P          Oil Street drainage works

¡P          Excavation / Construction of retaining wall/Approach Ramp /ADB

¡P          Bridge segment erections

¡P          Pre-bored H-pile for Approach Ramp

¡P          Hing Fat Street modification works

¡P          Bridge TA2 demolition

¡P          Abutment D12 construction

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

¡P          Diaphragm wall construction

¡P          Grouting

¡P          Construction of MVB

¡P          Pre-bored H-pile construction

¡P          Construction of concrete plug

¡P          Excavation and lateral support installation

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B

¡P          Tree protection works next to existing BGO,

¡P          Drainage improvement works,

¡P          Sheet piling works,

¡P          Excavation and Lateral Support for U-structure,

¡P          Pipe piling & grouting works,

¡P          Utility diversion works,

¡P          Retaining wall works

¡P          ELS works,

¡P          Diaphragm Wall, Barrette construction and king post installation works

¡P          D-wall drill cutting works

¡P          Construction works for subway extension

 

Contract no. HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

¡P          West Ventilation Building Construction

¡P          East Ventilation Shaft Construction

¡P          Tunnel Thermal Barrier Construction

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w ¡V International Financial Centre East Podium and International Finance Centre West Podium and M8 ¡V City Hall on weekly basis in the reporting month.
  2. Four limit level exceedances were recorded at noise monitoring station M1a ¡V Habour Road Sports Center on 01, 08, 15 and 23 December 2015. The exceedances were concluded as non-project related.
  3. Two limit level exceedances were recorded at noise monitoring station M6 ¡V HK Baptist Church Henrietta Secondary School on 11 and 16 December 2015. The exceedances were concluded as non-project related.
  4. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot for construction activities at IEC bridge deck. No limit level exceedance was recorded in the reporting month.
  5. 24-hour real time noise monitoring was conducted at RTN2a ¡V Hong Kong Electric Centre. No project related limit level exceedance was recorded in the reporting month.
  6. 24-hour real time noise monitoring was conducted at RTN3 ¡V Yu Lee Mo Fan Memorial School. No limit level exceedance was recorded in the reporting month.
  7. 24-hour real time noise monitoring was conducted at RTN4 ¡V Causeway Bay Community Centre. No project related exceedance was recorded in the reporting month.
  8. Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.
  9. Real time noise monitoring station at Oil Street Community Liaison Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5 Oct 2012 which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  10. Real-time noise baseline capturing was conducted from 21 Sep 2012 to 04 Oct 2012 at RTN3-Po Leung Kuk Yu Lee Mo Fan Memorial School.
  11. Real-time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.
  12. Causeway Bay Community Centre has granted permission for set up of real time noise monitoring station on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The Baseline noise level of RTN4- Causeway Bay Community Centre will adopt the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
  13. According to clause 3.1 stated in EP-364/2009/B, ¡§the real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern Corridor¡¨. IEC demolition associated construction works was commenced on 3 Feb 2013 and Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.
  14. Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.
  15. With respect to the completion of Victoria Car Park refurbishment, the noise monitoring at M4b-Victora Center was reverted from 3/F to 2/F since 24 June 2014.

 

Air Quality Monitoring

  1. With respect to the area handover, the air quality monitoring station CMA5a at Children Playgrounds opposite to the Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The station reference and location ID of the air quality monitoring station CMA5a was updated as CMA5b and Pedestrian Plaza respectively.
  2. Due to extension of site boundary by contractor of HY/2009/19, location of air quality monitoring station CMA1b ¡V Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  3. The location ID of air quality monitoring station CMA1b was updated as Oil Street Site Office in April 2013.
  4. With respect to the removal of Oil Street Site Office, the respective air quality monitoring station CMA1b was finely adjusted on 11 September 2015.
  5. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b ¡V Oil Street Site Office; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a ¡V Society for the Prevention of Cruelty to Animals; CMA5b - Pedestrian Plaza; MA1e and MA1w ¡V International Finance Centre eastern and western podium on every six days basis.
  6. Due to interruption of electricity supply, the 24hr TSP monitoring at CMA5b was rescheduled from 02 December 2015 to 03 December 2016.
  7. No action or limit level exceedance for TSP monitoring was recorded in the reporting month.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. Two environmental complaints were received in the reporting month.

 

  1. First public complaint regarding construction dust impact referred by EPD was received by ET on 04 December 2015 (EPD Ref: H04/RS/00028924-15). The complainant reported that excessive construction dust was generated from the construction site near Two International Finance Centre at Finance Street, Central

 

ET confirmed with the Resident Site Staff that bridge works and drains/ sewers construction at the concerned location was undertaken by Contract HY/2009/18 on 12 November 2015.  A stockpile which would be reused for backfilling was stored at the concerned location by Contract HY/2009/18 on 12 November 2015.

 

Mitigation measures implemented by the Contractor for the above construction works including covering of idled portion of stockpile and dampening of the exposed stockpile was implemented for the stockpile at the concerned location.

 

According to relevant site records confirmed by RSS, bridge works and drains/ sewers construction at the concerned location was undertaken by Contractor of HY/2009/18 on 12 November 2015 and a stockpile which would be reused for backfilling was stored at the concerned location. Mitigation measures including covering of idled portion of stockpile and dampening of the exposed stockpile was implemented for the stockpile at the concerned location.

 

In view of the public concern on potential dust impact at the concerned location, the Contractor of HY/2009/18 rearranged the works sequence and placed concrete blocks at the bridge retaining wall to allow for early commencement of backfilling on 19 November 2015 to minimize the size of the stockpile at an earlier stage. Additional water sprinklers were installed on 27 November 2015 to further enhance the dampening of the stockpile surface during excavation.

 

Follow-up inspection was conducted during weekly environmental inspection on 10 December 2015 and mitigation measures including covering of stockpile stored at the concerned location was implemented while it was observed that stockpiles stored near Man Chiu Street was not properly covered. The Contractor of HY/2009/18 was advised to promptly provide covering to all idled stockpile stored on site and the Contractor was reminded to enhance the watering during excavated material handling near the concerned location. Further follow up inspection was conducted on 17 December 2015 and mitigation measures including covering and watering for idle stockpile and material handling were implemented.

 

  1. Second public complaint regarding noise impact referred by RSS was received by ET on 16 December 2015 (ICC Case Ref.: 2-1656689815 dated 14 December 2015). The complainant reported that incessant noise emanating from the construction site of the Island Eastern Corridor Link that forms part of the Central-Wanchai Bypass Project.

 

Over the past couple of weeks, there have been loud mechanical pounding at the construction site over the reclaimed area between Blocks 10 and 11 of City Garden. As can be seen, machines have been breaking open the concrete paved on top of the reclaimed area. Work often starts well before 9am on weekdays and, barring a brief period of lull during lunch hours, would often continue unabated until after 5pm. Although I note that certain noise reduction measures have been put into place (e.g. the erection of flimsy noise barriers around the work area), the noise created is still enormous, and this has become a significant nuisance for residents living in nearby blocks of our estate, especially children and the elderly who have to stay at home for longer hours.

 

ET confirmed with the Resident Site Staff that concreting breaking works was carried out with one breaker on 7, 9, 11, 12 and 14 December 2015 and the breaking works at the concerned location were completed on 14 December 2015 morning. Noise mitigation measures including temporary noise barriers near the point of breaking and covering the breaker with acoustic mat were provided during the concerned concrete breaking works.

 

According to information confirmed by RSS, concreting breaking works was carried out by one excavator mounted breaker on 7, 9, 11, 12 and 14 December 2015 and the concerned breaking works outside City Garden Block 10 and Block 11 was completed on 14 December 2015 morning. Noise mitigation measures including temporary noise barriers near the point of breaking and covering the breaker with acoustic mat were provided during the concerned concrete breaking works. Based on the further review on the record of the environmental inspection conducted on 09 December 2015, the Contractor of HY/2009/19 was reminded to temporary noise barrier provided for the pile cap demolition shall follow the Environmental Permit EP-364/2009/D requirement.

 

Follow up inspection was conducted during weekly environmental inspection on 17 December 2015, the concerned breaking works opposite to City Garden Block 10 and Block 11 was observed completed while the Contractor was reminded that the remaining section of temporary noise barrier in accordance with the latest Environmental Permit EP-364/2009/D shall be completed on site as soon as possible. According to the information provided by RSS, the temporary noise barrier in accordance with the Environmental Permit requirement opposite to City Garden was substantially completed on 21 December 2015. In view of the public concern, the Contractor was suggested to consider to review the works duration at daytime and conduct other future breaking works around the concerned location intermittently to minimize the potential noise nuisance caused to the surroundings.

 

  1. Referring to the complaint case regarding the illegal disposal of construction waste referred by EPD was received by ET on 17 November 2015, the updated 2nd and 3rd interim investigation report were submitted to the EPD on 17 December 2015 and 31 December 2015 respectively. In response to the complaint concern, additional water quality monitoring and additional site inspections have been conducted by the ET and the investigation findings were included in the interim investigation reports separately submitted to the EPD. In addition, the ET and IEC have conducted checking on the waste disposal records and site construction records with the CWB RSS team to confirm the key construction activities during the concerned period and the quantities of inert C&D material disposed. Upon further review on relevant records and follow up inspections on the implementation of site measures, the final investigation would be issued.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/18, HY/2009/19, HY/2010/08, HK/2009/01, HK/2009/02, HK/2012/08 and HY/2011/08 in this reporting period.
  2. Construction of bored pile E3B under HY/2009/17 was confirmed completed and the respective work area under FEP-03/364/2009 was handover and inspected under HY/2009/19 from 19 Dec 2012 onwards.
  3. Construction works under HK/2010/06 was confirmed completed and the respective work area under FEP-08/364/2009/A was handover and inspected under HK/2012/08 from 22 Sep 2014 onwards.
  4. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

Future Key Issues

  1. In the coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

¡P          Drainage works

¡P          Road works

¡P          Bridges construction

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

¡P          Stage 1 ,2 & 3 Backfilling works at CWB Tunnel top slab

¡P          Stage 2 Construction of slip road 3

¡P          Stage 3 RC structure for CWB Tunnel Bay 18 to 20

¡P          Removal of abandoned cooling main (P7/P9) at Convention Avenue

¡P          Reinstatement of outfall

¡P          Reinstatement of triangular planter at Fenwick Pier Street

¡P          Roadworks /drains for Expo Drive East

¡P          Stage 4 ELS works

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P          Completion of road side barriers

¡P          Backfilling works

¡P          Cutting the top part of diaphragm wall

¡P          Strut layer S6 lateral support installation

¡P          Breaking through bulkhead wall BW3

¡P          Pouring blinding layer concrete

¡P          Tunnel construction at west side

¡P          Waterproofing layer application

¡P          Ground investigation works for bored piles and diaphragm wall

¡P          Bored pile construction

¡P          Pre-treatment works and guide wall construction for diaphragm wall

¡P          Diaphragm wall construction

¡P          Extraction of the temporary sheetpile seawall and removal of the temporary seawall blocks near the interface between Portion 2 and Portion 5

 

 

 

 

 

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P          Remedial works at Mined Tunnel

¡P          Excavation and RC structure works at TPCWAW

¡P          Remaining works inside tunnel at TS4 and TPCWAE

¡P          Removal of standby Dewatering System and monitoring instrument along Hung Hing road

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

¡P          Pier construction for IEC

¡P          Construction of EVB

¡P          Column modification at F1 to F8

¡P          Watson Road laying of new water pipe

¡P          Oil Street drainage works

¡P          Excavation / Construction of retaining wall/Approach Ramp/ADB

¡P          Bridge segment erections

¡P          Pre-bored H-pile for Approach Ramp

¡P          Hing Fat Street modification works

¡P          Bridge TA2 demolition

¡P          Abutment D12 construction

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

¡P          Diaphragm wall construction

¡P          Grouting

¡P          Construction of MVB

¡P          Pre-bored H-pile construction

¡P          Construction of concrete plug

¡P          Excavation and lateral support installation

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009

¡P          Tree protection works next to existing BGO,

¡P          Drainage improvement works,

¡P          Sheet piling works,

¡P          Excavation and Lateral Support for U-structure,

¡P          Pipe piling & grouting works,

¡P          Utility diversion works,

¡P          Retaining wall works

¡P          ELS works,

¡P          Diaphragm Wall, Barrette construction and king post installation works

¡P          D-wall drill cutting works

¡P          Construction works for subway extension

 

Contract no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

¡P          West Ventilation Building Construction

¡P          East Ventilation Shaft Construction

¡P          Tunnel Thermal Barrier Construction

1            Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/C and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/C, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B during the period 28 November 2015 to 26 December 2015.

1.2          Structure of the Report

 

Section 1          Introduction ¡V details the scope and structure of the report.

 

Section 2          Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8        Environmental Site Audit ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2      Project Background

2.1          Background

2.1.1.     ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central ¡V Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

¡P      A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

¡P      The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

¡P      Tunnel control buildings and ventilation buildings;

¡P      Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

¡P      Associated road lighting, road signing, traffic control and surveillance system; and

¡P      Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010 (Completed)

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works

 

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP1,DP3

13 July 2011

HY/2009/19

Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

10 March 2014

HY/2010/08

Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer¡¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 3388

3912 3010

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Manager

Mr. Simon Liu

2162 9909

2634 1626

Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Terry Tsang

6683 9394

Environmental Officer

Ms. Wendy Ng

9803 0057

Assistant Environmental Engineer

Ms. Connie Chan

6157 7057

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. K.K. Yuen

3658-3002

2827 9996

 

Project Manager

Mr. Paul Yu

3658 3085

Environmental Officer

Mr. C.P. Ho

9191 8856

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

Project Manager

Mr. David Lau

3758 8879

2570 8013

Deputy Project Manager

Mr. William Luk

9456 9819

Deputy Site Agent

Eric Fong

6191 9337

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Environmental Engineer

Mr. Calvin Leung

9286 9208

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Jimmy Chu

2214 7700

2140 6799

Deputy Site Agent

Mr. Bob Yeung

2214 7703

Environmental Officer

Ms. Lighting Chan

2823 1161

Assistant Environmental Engineer

Mr. Christy So

3937 1065

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. Chris Leung

3557 6393

2865 5229

Site Manager

Mr. Y. Huo

3557 6368

2566 2192

Contractor¡¦s Representative

Mr. Andrew Wong

3557 6371

Environmental Officer

Mr. Andy Mak

3557 6215

Environmental Supervisor

Mr. Harry Wong

3557 6348

China State- Leader JV

Contractor under Contract no. HK/2012/08

Project Director

Mr. C.N. Lai

9137 1811

2877 1522

Project Manager

Mr. Eddie Chung

9193 8871

Site Agent

Mr. Keith Tse

9095 7922

Environmental Officer

Mr. James MA

9130 9549

Environmental Supervisor

Mr. Y.L. Ho

6050 4919

China State

Contractor under Contract no.HY/2010/08

Project Director

Cheung Kit Cheung

3557 6399

2566 8061

Project Manager

Chan Ying Lun

9812 0592

Deputy Project Manager

Chris Leung

3467 4299

Site Agent

Dr. Dave Chan

3467 4277

Environmental Officer

Mr. C.M. Wong

3557 6464

Environmental Supervisor

Mr. Louis Lam Tsz Kwan

3557 6470

Leighton Joint Venture

Contractor under Contract no. HY/2011/08

Project Manager

Paul Evans

2823 1111

21406799

Site Agent

Colman Wong

9730 0806

Environmental Officer

Malcom Leung

3973 0850

Environmental Supervisor

Christy So

3973 1065

Ramboll Environ Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

 

2.4.3.     In this reporting month, the principal work activities of individual contracts are included as follows:

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

¡P          Drainage works

¡P          Road works

¡P          Bridges construction

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

¡P          Stage 1 & 2 Backfilling works at CWB Tunnel top slab

¡P          Construction of slip road 2 and slip road 3

¡P          Stage 3 RC structure for CWB Tunnel Bay 18 to 20

¡P          Removal of abandoned cooling main (P7/P9) at Convention Avenue

¡P          Reinstatement of outfall was

¡P          Reinstatement of triangular planter at Fenwick Pier Street

¡P          Roadworks /drains for Expo Drive East

¡P          Stage 4 ELS works

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009                                     

¡P          Removal of stockpile of material, site clearance works at Tunnel Portion 1.

¡P          Construction of road side barriers

¡P          Backfilling works and access shaft construction

¡P          Construction of road side barriers

¡P           Struts installation for layer S6

¡P          Excavation for layer S6 and formation level

¡P          Construction of blinding layer

¡P          Breaking through bulkhead wall BW3

¡P          Ground investigation works

¡P          Bored pile construction

¡P          Extraction of the temporary sheet pile seawall and removal of the temporary seawall blocks near the interface between Portion 2 and Portion 5.

¡P          Setting up of silo tanks, pre-treatment works for diaphragm wall construction

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

¡P          Construction roadside barrier at Mined Tunnel

¡P          Rock excavation at TPCWAW

¡P          Demolition of bulkhead wall between TPCWAE and TPCWAW

¡P          Construction RC structure at TPCWAW

¡P          Remaining works inside tunnel at TS4 and TPCWAE

¡P          Removal of standby Dewatering System and monitoring instrument along Hung Hing road

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

¡P          Pier construction for IEC

¡P          Construction of EVB

¡P          Column modification at F1 to F8

¡P          Bridge E deck construction

¡P          Watson Road laying of new water pipe

¡P          Oil Street drainage works

¡P          Excavation / Construction of retaining wall/Approach Ramp /ADB

¡P          Bridge segment erections

¡P          Pre-bored H-pile for Approach Ramp

¡P          Hing Fat Street modification works

¡P          Bridge TA2 demolition

¡P          Abutment D12 construction

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

¡P          Diaphragm wall construction

¡P          Grouting

¡P          Construction of MVB

¡P          Pre-bored H-pile construction

¡P          Construction of concrete plug

¡P          Excavation and lateral support installation

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B

¡P          Tree protection works next to existing BGO,

¡P          Drainage improvement works,

¡P          Sheet piling works,

¡P          Excavation and Lateral Support for U-structure,

¡P          Pipe piling & grouting works,

¡P          Utility diversion works,

¡P          Retaining wall works

¡P          ELS works,

¡P          Diaphragm Wall, Barrette construction and king post installation works

¡P          D-wall drill cutting works

¡P          Construction works for subway extension

 

Contract no. HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

¡P          West Ventilation Building Construction

¡P          East Ventilation Shaft Construction

¡P          Tunnel Thermal Barrier Construction

 

2.4.4.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

¡P          Drainage works

¡P          Road works

¡P          Bridges construction

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

¡P          Stage 1 ,2 & 3 Backfilling works at CWB Tunnel top slab

¡P          Stage 2 Construction of slip road 3

¡P          Stage 3 RC structure for CWB Tunnel Bay 18 to 20

¡P          Removal of abandoned cooling main (P7/P9) at Convention Avenue

¡P          Reinstatement of outfall

¡P          Reinstatement of triangular planter at Fenwick Pier Street

¡P          Roadworks /drains for Expo Drive East

¡P          Stage 4 ELS works

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P          Completion of road side barriers

¡P          Backfilling works

¡P          Cutting the top part of diaphragm wall

¡P          Strut layer S6 lateral support installation

¡P          Breaking through bulkhead wall BW3

¡P          Pouring blinding layer concrete

¡P          Tunnel construction at west side

¡P          Waterproofing layer application

¡P          Ground investigation works for bored piles and diaphragm wall

¡P          Bored pile construction

¡P          Pre-treatment works and guide wall construction for diaphragm wall

¡P          Diaphragm wall construction

¡P          Extraction of the temporary sheetpile seawall and removal of the temporary seawall blocks near the interface between Portion 2 and Portion 5

 

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P          Remedial works at Mined Tunnel

¡P          Excavation and RC structure works at TPCWAW

¡P          Remaining works inside tunnel at TS4 and TPCWAE

¡P          Removal of standby Dewatering System and monitoring instrument along Hung Hing road

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

¡P          Pier construction for IEC

¡P          Construction of EVB

¡P          Column modification at F1 to F8

¡P          Watson Road laying of new water pipe

¡P          Oil Street drainage works

¡P          Excavation / Construction of retaining wall/Approach Ramp/ADB

¡P          Bridge segment erections

¡P          Pre-bored H-pile for Approach Ramp

¡P          Hing Fat Street modification works

¡P          Bridge TA2 demolition

¡P          Abutment D12 construction

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

¡P          Diaphragm wall construction

¡P          Grouting

¡P          Construction of MVB

¡P          Pre-bored H-pile construction

¡P          Construction of concrete plug

¡P          Excavation and lateral support installation

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009

¡P          Tree protection works next to existing BGO,

¡P          Drainage improvement works,

¡P          Sheet piling works,

¡P          Excavation and Lateral Support for U-structure,

¡P          Pipe piling & grouting works,

¡P          Utility diversion works,

¡P          Retaining wall works

¡P          ELS works,

¡P          Diaphragm Wall, Barrette construction and king post installation works

¡P          D-wall drill cutting works

¡P          Construction works for subway extension

 

Contract no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

¡P          West Ventilation Building Construction

¡P          East Ventilation Shaft Construction

¡P          Tunnel Thermal Barrier Construction

3         status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

20 Sep 2012

Superseded

Environmental Permit

EP-364/2009/C

11 Jul 2014

Superseded

Environmental Permit

EP-364/2009/D

24 Nov 2015

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Surrendered

Further Environmental Permit

FEP-06/356/2009

5 March 2013

Valid

Further Environmental Permit

FEP-07/356/2009

26 July 2013

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Superseded

Further Environmental Permit

FEP-07/364/2009/D

24 Nov 2015

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 June 2012

Surrendered

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

Valid

Further Environmental Permit

FEP-10/364/2009/B

26 July 2013

Valid

Further Environmental Permit

FEP-11/364/2009/B

2 May 2014

Valid

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

3.1.3.     The construction works was completed and the FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.

Contract no. 04/HY/2006 ¡V Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.     The construction works was completed, and the FEP-04/HY/2006 was surrendered by the Contractor on 11 February 2011.

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

3.1.5.     The construction works was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

3.1.6.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.

Table 3.2    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

 

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

06 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-pilling equipment

GW-RS0706-15

30 Jun 2015

02 Jul 2015 to     01 Jan 2016

Valid

 

GW-RS0803-15

28 Jul 2015

21 Aug 2015 to 20 Feb 2016

Valid

 

GW-RS0804-15

28 Jul 2015

22 Aug 2015 to 21 Feb 2016

Valid

 

GW-RS0868-15

13 Aug 2015

14 Aug 2015 to 13 Feb 2016

Valid

GW-RS1025-15

22 Sep 2015

24 Sep 2015 to 23 Mar 2016

Valid

GW-RS1031-15

22 Sep 2015

29 Sep 2015 to 24 Mar 2016

Cancelled

 

GW-RS1134-15

23 Oct 2015

08 Nov 2015 to 07 May 2016

Valid

 

GW-RS1135-15

23 Oct 2015

26 Nov 2015 to 25 May 2016

Valid

 

GW-RS1228-15

13 Nov 2015

16 Nov 2015 to 13 May 2016

Valid

 

GW-RS1309-15

27 Nov 2015

30 Nov 2015 to 26 May 2016

Valid

Discharge Licence

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

WT00021138-2015

17 Mar 2014

31 Mar 2020

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

Dumping Permit

(Type 1 ¡V Open Sea Disposal)

EP_MD_16-018

02 Jun 2015

13 Oct 2015 to 12 Apr 2016

Valid

 

Table 3.3    Summary of submission status under FEP-02/364/2009

EP Condition

Submission

Date of Submission

Condition 2.7 & 2.8

Works Schedule and Location Plan

18 May 2011

Condition 2.6

Environmental Management Organization Chart

18 May 2011

Condition 1.12

Commencement Date of Works

20 Jun 2011

Condition 2.9

Noise Management Plan

10 Jun 2011

Condition 2.11

Landscape Plan (Rev.4)

8 July 2015

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

3.1.7.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.

Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for non-pilling equipment

GW-RS0723-15

2 Jul 2015

7 July 2015 to 06 Jan 2016

Cancelled

GW-RS0831-15

31 Jul 2015

03 Aug 2015 to 28 Jan 2016

Cancelled

GW-RS0610-15

10 Jun 2015

22 Jun 2015 to 21 Dec 2015

Expired

GW-RS0637-15

11 Jun 2015

18 Jun 2015 to 08 Dec 2015

Expired

GW-RS0709-15

30 Jun 2015

02 July 2015 to 01 Jan 2016

Valid

GW-RS0716-15

30 Jun 2015

04 July 2015 to 27 Dec 2015

Expired

GW-RS0981-15

07 Sep 2015

09 Sep 2015 to 06 Mar 2016

Cancelled

GW-RS1004-15

15 Sep 2015

17 Sep 2015 to 16 Dec 2015

Expired

GW-RS1006-15

15 Sep 2015

18 Sep 2015 to 14 Mar 2016

Valid

GW-RS1099-15

08 Oct 2015

08 Oct 2015 to 30 Nov 2015

Expired

GW-RS1121-15

20 Oct 2015

22 Oct 2015 to 18 Apr 2016

Cancelled

GW-RS1150-15

26 Oct 2015

28 Oct 2015 to 27 Apr 2016

Valid

GW-RS1187-15

28 Oct 2015

30 Oct 2015 to 27 Apr 2016

Valid

GW-RS1413-15

24 Dec 2015

02 Jan 2016 to 01 Jul 2016

Valid

Water Discharge License

WT00008982-2011

26 April 2011

30 April 2016

Valid

WT00009691-2011

01 Aug 2011

31 July 2016

Valid

WT00022295-2015

12 Aug 2015

31 July 2020

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/16-034

26 Jun 2015

01 Jul 2015 to 31 Dec 2015

Valid

EP/MD/16-146

24 Dec 2015

01 Jan 2016 to 30 Jun 2016

Valid

 

Table 3.5    Summary of submission status under FEP-01/364/2009

EP Condition

Submission

Date of Submission

Condition 2.7 and  2.8

Works Schedule and Location Plan

14 Jun 2011

Condition 2.6

Environmental Management Organization Chart

14 Jun 2011

Condition 1.12

Commencement Date of Works

21 Jun 2011

Condition 2.11

Landscape Plan (Revision B)

20 Nov 2012

Condition 2.9

Noise Management Plan (Revision B)

13 Jan 2012

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

3.1.8.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table 3.7.

Table 3.6    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Permit / Licence / Notification / Approval

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Permit issued

Valid

Notification of Works Under APCO

322293

07 Oct 2010

Notified

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0719-15

3 July 2015

06 Jul 2015 to

31 Dec 2015

Valid

GW-RS0830-15

29 July 2014

30 Jul 2015 to 29 Jan 2016

Valid

GW-RS1206-15

06 Nov 2015

12 Nov 2015 to
31 Mar 2016

Valid

 

GW-RS1383-15

14 Dec 2015

19 Dec 2015 to

27 Mar 2016

Valid

 

GW-RS1415-15

24 Dec 2015

01 Jan 2016 to

30 Jun 2016

Valid

Discharge Licenses

WT00012998-2012

25 May 2012

31 Jan 2016

Cancelled

WT00013967-2012

17 Sep 2012

30 Sep 2017

Cancelled

WT00014966-2013

08 Jan 2013

31 Jan 2018

Cancelled

WT00020398-2014

21 Nov 2014

31 Jan 2016

Valid

WT00020725-2015

14 Jan 2015

30 Jul 2017

Valid

Registration as a Chemical Waste Producer

WPN: 8335-121-L1048-04

17 Dec 2010

N/A

Registration completed

Billing Account under Waste Disposal Ordinance (Land)

Account No.: 7011587

11 Oct 2010

Account approved

Valid

 

Table 3.7    Summary of submission status under FEP-05/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

01 March 2011

Condition 2.10

Landscape Plan (Rev. 6)

19 May 2014

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

3.1.9.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.

Table 3.8    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

N/A

Valid

FEP-04/356/2009

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0679-15

29 Jun 2015

01 Jul 2015 to 31 Dec 2015

Valid

GW-RS893-15

17 Aug 2015

17 Aug 2015 to 16 Feb 2016

Valid

GW-RS0990-15

10 Sep 2015

10 Sep 2015 to 09 Mar 2016

Valid

GW-RS1160-15

26 Oct 2015

28 Oct 2015 to 25 Apr 2016

Valid

 

GW-RS1303-15

26 Nov 2015

26 Nov 2015 to 25 May 2016

Valid

Registration as a Chemical Waste Producer

WPN: 5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

27 Sep 2010 to

27 Jan 2016

Valid

Billing Account under Waste Disposal Ordinance

(Disposal by Vessel)

7011761

26 Jun 2015

17 Oct 2015 to 17 Jan 2016

Valid

Water Discharge License  (TS1)

WT00008780-2011

24 Nov 2011

24 Nov 2011 to 31 Mar 2016

Valid

Water Discharge License (Discharge at  CHT area)

WT00019250-2014

6 Jun 2014

06 Jun 2014 to 31 May 2016

Valid

Water Discharge License (Discharge at  TPCWAE)

WT00018167-2014

17 Jan 2014

17 Jan 2014 to 31 Dec 2015

Valid

Water Discharge License (Discharge at TS4)

WT00018542-2014

17 Mar 2014

17 Mar 2014 to 31 Jan 2016

Cancelled

Water Discharge Licence (Discharge at  TPCWAW)

WT00020601-2014

18 Mar 2015

18 Mar 2015 to 31 Mar 2017

Valid

 

Table 3.9    Summary of submission status under FEP-06/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 Mar 2011

Amendment for Management Organization of Main Construction Companies

16 May 2011

Condition 2.7

Works Schedule

15 Mar 2011

Condition 2.8

Location Plan

15 Mar 2011

Condition 2.9

Noise Management Plan

6 May 2011

Condition 2.10

Landscape Plan (Rev.3)

30 Jan 2015

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

3.1.10.   The current status on licences and/or permits on environmental protection pertinent and submission under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table 3.11.

Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

N/A

Superseded

FEP-07/364/2009/D

24 Nov 2015

N/A

Valid

Notification of Works Under APCO

326160

24 Jan 2011

N/A

Valid

Registration as a Waste Producer

7012306

10 Feb 2011

N/A

Valid

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

N/A

Valid

Application for Vessel Disposal

7012306

21 July 2011

N/A

Valid

Construction Noise Permits (CNP) for non-piling equipment

GW-RS0741-15

10 Jul 2015

23 Jul 2015 to

22 Jan 2016

Cancelled

GW-RS0671-15

18 Jun 2015

20 Jun 2015 to

17 Dec 2015

Expired

GW-RS0869-15

13 Aug 2015

15 Aug 2015 to

12 Feb 2016

Valid

GW-RS0909-15

21 Aug 2015

21 Aug 2015 to    20 Feb 2016

Valid

GW-RS1036-15

22 Sep 2015

24 Sep 2015 to

23 Mar 2016

Cancelled

GW-RS1189-15

06 Nov 2015

09 Nov 2015 to

08 Dec 2015

Expired

GW-RS1324-15

01 Dec 2015

08 Dec 2015 to

07 Jun 2016

Valid

GW-RS1398-15

17-Jun-15

18 Dec 2015 to

17 Jun 2016

Valid

Water Discharge License

WT00010093-2011

17 Aug 2012

30 Sep 2016

Valid

WT00010865-2011

03 Nov 2011

30 Nov 2016

Cancelled

Dumping Permit (Approach Ramp) (Type 1 ¡V Open Sea Disposal)

EP/MD/16-092

20 Nov 2015

15 May 2016

Valid

Dumping Permit (Approach Ramp) (Type 2 ¡V Confined Marine Disposal)

EP/MD/16-093

20 Nov 2015

19 Dec 2015

Expired

 

 

Table 3.11   Summary of submission status under FEP-07/364/2009/D

EP Condition

Submission

Date of Submission

Condition 2.13

Landscape Plan (Rev.3)

19 August 2014

Condition 2.9

Noise Management Plan (Rev.4)

2 Feb 2015

 

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

 

3.1.11    The current status on licences and/or permits on environmental protection pertinent and submission under FEP-09/364/2009/B for contract no. HK/2012/08 showed in Table 3.12 and Table 3.13.

   

Table 3.12  Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

N/A

Valid

FEP-06/356/2009

5 March 2013

N/A

Valid

Notification of Works Under APCO

355439

4 Feb 2013

N/A

Valid

Registration as a Chemical Waste Producer

5213-134-C3790-01

8 Mar 2013

N/A

Valid

Billing Account under Waste Disposal Ordinance

7016883

18 Feb 2013

18 Jul 2017

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0838-15

31 Jul 2015

03 Aug 2015 to 02 Feb 2016

Valid

GW-RS0976-15

7 Sep 2015

23 Sep 2015 to 22 Mar 2016

Valid

Water Discharge Licence

WT00018223-2014

28 Jan 2014

31 Jan 2019

Cancelled

WT00020594-2014

22 Dec 2014

31 Jan 2019

Valid

 

 

Table 3.13  Summary of submission status under FEP-09/364/2009/B

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan (Rev.2)

9 July 2013

Condition 2.14

Landscape Plan (Rev.4)

24 August 2015

 

 

Contract no. HY/2010/08 ¡VCentral ¡V Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8)

3.1.12    The current status on licences and/or permits on environmental protection pertinent and submission under FEP-10/364/2009/B for contract no. HK/2012/08 showed in Table 3.14 and Table 3.15.

Table 3.14  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-10/364/2009/B

26 Jul 2013

NA

Valid

FEP-07/356/2009

26 Jul 2013

NA

Valid

Notification of Works Under APCO

357176

2013-04-02

NIL

Valid

Registration as a Chemical Waste Producer

WPN5213-147-C1169-44

2013-03-27

NIL

Valid

Billing Account under Waste Disposal Ordinance

7017170

2013-03-27

NIL

Valid

Water Discharge License

WT0001651-2013

2013-07-09

2018-07-28

Cancelled

WT00020468-2014

2014-12-03

2018-07-31

Valid

Construction Noise Permit (CNP) for non-pilling works

GW-RS0620-15

11 Jun 2015

11 Jun 2015 to 10 Dec 2015

Cancelled

GW-RS0811-15

24 Jul 2015

29 Jul 2015 to 28 Jan 2016

Cancelled

GW-RS0972-15

08 Sep 2015

09 Sep 2015 to 08 Mar 2016

Valid

GW-RS0765-15

13 Jul 2015

13 July 2015 to 12 Jan 2016

Valid

GW-RS0920-15

26 Aug 2015

28 Aug 2015 to 24 Feb 2016

Valid

GW-RS0938-15

26 Aug 2015

28 Aug 2015 to 24 Feb 2016

Cancelled

GW-RS1039-15

23 Sep 2015

23 Sep 2015 to 21 Mar 2016

Cancelled

GW-RS1061-15

30 Sep 2015

02 Oct 2015 to 31 Mar 2016

Cancelled

GW-RS1063-15

30 Sep 2015

02 Oct 2015 to 31 Mar 2016

Cancelled

GW-RS1137-15

22 Oct 2015

22 Oct 2015 to 21 Apr 2016

Valid

GW-RS1141-15

20 Oct 2015

22 Oct 2015 to 21 Apr 2016

Valid

GW-RS1145-15

20 Oct 2015

22 Oct 2015 to 21 Apr 2016

Valid

GW-RS1262-15

17 Nov 2015

18 Nov 2015 to 16 May 2016

Valid

GW-RS1282-15

25 Nov 2015

25 Nov 2015 to 24 May 2016

Valid

 

Table 3.15  Summary of submission status under FEP-10/364/2009/B

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan (Rev.3)

03 January 2014

Condition 2.14

Landscape Plan (Rev.2)

19 May 2014

Condition 2.16

Additional Mitigation Plan (Rev.2)

18 February 2015

 

 

 

 

 

 

 

 

Contract no. HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/B

 

3.1.13    The current status on licenses and/or permits on environmental protection pertinent and submission under FEP-11/364/2009/B for contract no. HY/2011/08 showed in Table 3.16 and Table 3.17.

Table 3.16  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2011/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-11/364/2009/B

2 May 2014

N/A

Valid

Notification of Works Under APCO

LCAC-EN-LE-00017

7 Mar 2014

N/A

Valid

Registration as a Chemical Waste Producer

5213-121-L2837-01

21 May 2014

N/A

Valid

5213-151-L2837-02

09 Oct 2015

N/A

Registered

5213-134-L2898-01

16 Nov 2015

N/A

Registered

Billing Account under Waste Disposal Ordinance

7019640

27 Mar 2014

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS-0678-15

19 June 2015

26 Jun 2015 to

25 Dec 2015

Expired

GW-RS0738-15

06 July 2015

07 July 2015 to 31 Dec 2015

Valid

GW-RS0758-15

07 July 2015

08 July 2015 to 31 Dec 2015

Valid

GW-RS0856-15

10 Aug 2015

27 Aug 2015 to 26 Feb 2016

Valid

GW-RS1235-15

12 Nov 2015

18 Nov 2015 to
30 Apr 2016

Valid

GW-RS1423-15

24 Dec 2015

26 Dec 2015 to

31 May 2016

Valid

GW-RS1426-15

29 Dec 2015

01 Jan 2016 to

30 Jun 2016

Valid

GW-RS1433-15

29 Dec 2015

01 Jan 2016 to

30 Jun 2016

Valid

Water Discharge Licence

WT00020242-2014

04 Nov 2014

30 Nov 2019

Valid

WT00020246-2015

15 Jul 2015

31 Jul 2019

Valid

 

 

 

 

 

 

 

Table 3.17  Summary of submission status under FEP-11/364/2009/B

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan (Rev.2)

27 Jan 2015

Condition 2.14

Landscape Plan (Rev.2)

18 Feb 2015

Condition 2.13

Operational Air Quality Management Plan for West Ventilation Building (Rev.0)

25 Nov 2014

Condition 2.13

Operational Air Quality Management Plan for East Ventilation Building and East Vent Shaft  (Rev.0)

18 Feb 2015

4          Monitoring Requirements

4.1          Noise Monitoring

Noise Monitoring Stations

4.1.1.     The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1.  Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1    Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon-day Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

*M8

City Hall

* Remark 1: Location ID has been updated from M7 to M8 for City Hall

* Remark 2: M7e has become a reference station starting from 7 Aug 2012

 

Real time Noise Monitoring Stations

4.1.2.     The noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2    Real Time Noise Monitoring Stations

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitfield Depot

North Point

RTN2a

Electric Centre

North Point

RTN3

Po Leung Kuk Yu Lee Mo Fan Memorial School

Tin Hau

RTN4

Causeway Bay Community Centre

 

 

 

 

 

Noise Monitoring Parameters, Frequency and Duration

4.1.3.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.4.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

¡P      One set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.5.     Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 - hours basis when noise generating activities are underway:

¡P      One set of measurements between 0700 and 1900 hours on normal weekdays.

¡P      One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

¡P      One set of measurements between 2300 and 0700 hours on next day on everyday.

4.1.6.     If construction works are extended to include works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.7.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.8.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

4.1.9.     The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements will be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.2          Air Quality Monitoring

Air Quality Monitoring Stations

4.2.1.     The air quality monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3    Air Quality Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Site Office**

North Point (Re-commenced on 14 November 2011)

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5b

Pedestrian Plaza***

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (Western End of Podium)

Central

Remarks*: As per the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB site office at Wanchai Waterfront Promenade was renamed as remark.

Remarks**: The location ID of monitoring station CMA1b was updated as ¡§Oil Street Site Office¡¨ in April 2013.

Remarks***: The station ID and monitoring location was updated in December 2014 with respect to monitoring station relocation.

Air QUALITY Monitoring Parameters, Frequency and Duration

4.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six days should be undertaken when the highest dust impact occurs.


Sampling Procedure and Monitoring Equipment

4.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

¡P      0.6 ¡V 1.7 m3 per minute adjustable flow range;

¡P      Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

¡P      Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

¡P      Capable of providing a minimum exposed area of 406 cm2;

¡P      Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

¡P      Equipped with a shelter to protect the filter and sampler;

¡P      Incorporated with an electronic mass flow rate controller or other equivalent devices;

¡P      Equipped with a flow recorder for continuous monitoring;

¡P      Provided with a peaked roof inlet;

¡P      Incorporated with a manometer;

¡P      Able to hold and seal the filter paper to the sampler housing at horizontal position;

¡P      Easily changeable filter; and

¡P      Capable of operating continuously for a 24-hour period.

 

4.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.     Filter paper of size 8¡¨ x 10¡¨ shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24 hours and be pre-weighed before use for the sampling.

4.2.9.     After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.10.   All the collected samples shall be kept in a good condition for 6 months before disposal.

4.2.11.   Current calibration certificates of equipments are presented in Appendix 4.2.

5.0        Monitoring Results

5.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designated project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.     In the reporting month, the concurrent contracts are as follows:

Ÿ  Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

Ÿ  Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange

Ÿ  Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ  Contract no. HY/2010/08 ¡V Central- Wanchai Bypass Tunnel (Slip Road 8 Section)

Ÿ  Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre

Ÿ  Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass at Wan Chai East

Ÿ  Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai West

Ÿ  Contract no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB)¡V Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

5.0.3.     The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

 

 

 

 

5.1          Noise Monitoring Results

5.1.1       Monitoring for report of review baseline noise level was performed from 11 April 2011 to 8 June 2011.  Then the report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012.  The new baseline is used for the noise calculation starting from January 2012.

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

5.1.2       Noise monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2009/18 are summarized in Table 5.1 below:

Table 5.1    Noise Monitoring Stations for Contract no. HY/2009/18

Station

Description

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8

City Hall

* Remark: M7e has become a reference station starting from 7 Aug 2012

 

5.1.3       No action or limit level exceedance was recorded in this reporting month.

5.1.4       Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.1.5       The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.2 below.

 

Table 5.2    Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

 

5.1.6       Four limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 01, 08, 15 and 23 December 2015 in this reporting month.

5.1.7       Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 01, 08, 15 and 23 December 2015.  As such, the exceedance was considered as non-Project related.

5.1.8       Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.1.9       The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was commenced on 13 July 2011. The proposed divisions of noise monitoring stations are summarized in Table 5.3 below.

 

Table 5.3    Noise Monitoring Stations for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

5.1.10    No action or limit level exceedance was recorded in this reporting month.

5.1.11    Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

 

5.1.12    Noise monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.4 below.

 

Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/19

Station

Description

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

5.1.13    Two limit level exceedances were recorded at monitoring station M6 - HK Baptist Church Henrietta Secondary School on 11 and 16 December 2015 in this reporting month.

5.1.14    Major traffic noise observed during monitoring was considered as the major noise contribution. As such, the limit level exceedances were concluded as non-project related.

5.1.15    Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.  Details of the Notification of Exceedance can be referred in Appendix 6.2.

Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡VWanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B

5.1.16    The commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02 September 2013. The proposed divisions of noise monitoring stations are summarized in Table 5.5 below.

 

Table 5.5    Noise Monitoring Stations for Contract no. HY/2010/08

Station

Description

M3a

Tung Lo Wan Fire Station

5.1.17    No action or limit level exceedance was recorded in this reporting month.

5.1.18    Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. 

Contract no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡V Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

5.1.19    Noise monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2011/08 are summarized in Table 5.6 below:

Table 5.6    Noise Monitoring Stations for Contract no. HY/2011/08

Station

Description

M4b

Victoria Centre

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8

City Hall

* Remark: M7e has become a reference station starting from 7 Aug 2012

5.1.20    No action or limit level exceedance was recorded in this reporting month.

5.1.21    Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

 

5.2       Real Time Noise Monitoring Results

5.2.1.     As confirmed by CWB RSS, the IECL parapet removal operations and associated construction work was commenced in June 2013.  Liaison was conducted with HK Baptist Church Henrietta Secondary School, Po Leung Kuk Yu Lee Mo Fan Memorial School and Causeway Bay Community Centre regarding the set up of RTN3 real time noise monitoring station. 

5.2.2.     Causeway Bay Community Centre has granted permission for set up on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The baseline noise level of RTN4- Causeway Bay Community Centre has adopted the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.

5.2.3.     Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.

5.2.4.     Po Leung Kuk Yu Lee Mo Fan Memorial School granted permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012. Real time noise baseline capturing was conducted during time period without construction work from 21 Sep 2012 to 04 Oct 2012.

5.2.5.     Real time noise monitoring at RTN3 ¡V Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.

5.2.6.     Oil Street Community Liaison Centre was confirmed to be demolished in mid-October by CWB RSS.  This presented a need for relocation of RTN2 ¡V Oil Street Community Liaison Centre.  After liaison with Hong Kong Electric, permission was granted on 21 Sep 2012 for real time noise monitoring set up at City Garden Electric Centre (RTN2a ¡V Electric Centre), which is a representative of the noise sensitive receiver City Garden.

5.2.7.     RTN2 previously located at oil Street Community Liaison Centre was relocated to Hong Kong Electric Centre on 5 Oct 2012, which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted at Electric Centre from 4 December 2009 to 17 December 2009.

5.2.8.     Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.

 

 

 

 

 

 

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

5.2.9.     The proposed division of noise monitoring stations are summarized in Table 5.7 below. Real time noise monitoring for major construction works under contract no. HY/2009/19 was commenced on 24 April 2011.

Table 5.7    Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitfield Depot

RTN2a

North Point

Electric Centre

RTN3

North Point

Po Leung Kuk Yu Lee Mo Fan Memorial School

RTN4

Tin Hau

Causeway Bay Community Centre

* Real time noise monitoring results and graphical presentation during restrict hours and night time period are for information only and noise during CNP period shall be controlled under NCO.

5.2.10.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

5.2.11.   Limit level exceedance was recorded at RTN2a-Electric Centre on 15 December 2015 during daytime in the reporting month. On 15 December 2015, concreting was undertaken by Contract HY/2009/19 while steel bar cutting works by saw cutter for Hong Kong Electric Centre was conducted at the roof top by non-CWB Contractor immediately next to the noise monitoring station and was considered as major noise contribution. As such, the exceedance was considered as non-Project related.

5.2.12.   No limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School during in the reporting month.

5.2.13.   Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre during daytime on 02 December 2015 in the reporting month. On 02 December 2015, only steel mould dismantling works was undertaken by Contract HY/2009/19 during monitoring while scaffold dismantling and manual handling of material was observed undertaken by non-CWB Contractor at Causeway Bay Community Centre in close proximity to the monitoring station and was considered as the major noise contribution. As such, the exceedances were considered as non-Project related.

5.2.14.   Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4.

 

 

Contract no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡V Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

5.2.15.   The proposed division of noise monitoring stations are summarized in Table 5.8 below. Real time noise monitoring for major construction works under contract no. HY/2011/08 was commenced on 19 March 2015.

Table 5.8    Real Time Noise Monitoring Stations for Contract no. HY/2011/08

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitfield Depot

* Real time noise monitoring results and graphical presentation during restrict hours and night time period are for information only and noise during CNP period shall be controlled under NCO.

5.2.16.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

5.3       Air Quality Monitoring Results

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

5.3.1       Air quality monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011. The proposed division of air quality monitoring stations are summarized in Table 5.9 below.

Table 5.9 Air Quality Monitoring Stations for Contract no. HY/2009/18

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

 

5.3.2       No exceedance was recorded in the reporting month.

5.3.3       Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

5.3.4       The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized in Table 5.10 below.

Table 5.10 Air Quality Monitoring Station for Contract no. HK/2009/01

Station

Description

CMA5b

Pedestrian Plaza

5.3.5       No exceedance was recorded in the reporting month.

5.3.6       Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

 

 

 

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.3.7       The commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of air quality monitoring stations are summarized in Table 5.11 below.

Table 5.11 Air Quality Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

5.3.8       No exceedance was recorded in the reporting month.

5.3.9       Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.3.10    The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized in Table 5.12 below.

Table 5.12 Air Quality Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

5.3.11    No exceedance was recorded in the reporting month.

5.3.12    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

5.3.13    The proposed division of air quality monitoring stations are summarized in Table 5.13 below. Air quality monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.

Table 5.13 Air Quality Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil Street Site Office

CMA2a

Causeway Bay Community Centre

5.3.14    No exceedance was recorded in the reporting month.

5.3.15    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3.

Contract no. HK/2012/08- Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai West

5.3.16    The commencement of construction works for Contract no. HK/2012/08 under FEP-09/364/2009/C was on May 2014. Air quality monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized in Table 5.14 below.

Table 5.14 Air Quality Monitoring Station for Contract no. HK/2012/08

Station

Description

CMA5b

Pedestrian Plaza

5.3.17    No exceedance was recorded in the reporting month.

5.3.18    Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡VWanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B

5.3.19    The commencement of construction works for Contract no. HY/2010/08 under FEP-09/364/2009/B was on July 2014. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized in Table 5.15 below.

Table 5.15 Air Quality Monitoring Station for Contract no. HY/2010/08

Station

Description

CMA3a

CWB PRE Site Office

5.3.20    No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

 

 

 

 

Contract no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡V Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

5.3.21    Air quality monitoring for the Central Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011. The proposed division of air quality monitoring stations are summarized in Table 5.16 below.

Table 5.16   Air Quality Monitoring Stations for Contract no. HY/2011/08

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

CMA1b

Oil Street Site Office

CMA2a

Causeway Bay Community Centre

 

5.3.22    No exceedance was recorded in the reporting month.

5.3.23    Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

5.4       Waste Monitoring Results

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

5.4.1.     Inert C&D wastes and non-inert C&D wastes were disposed in this reporting month. Details of the waste flow table are summarized in Table 5.17.

Table 5.17  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

Nil

106130.58

TKO137, TM38

Inert C&D materials recycled, m3

6472.5

97630.03

N/A

Non-inert C&D materials disposed, m3

34.05

3728.2

SENT Landfill

Non-inert C&D materials recycled, kg

42950

1065766

N/A

Chemical waste disposed, kg

20

10400

N/A

Marine Sediment

 (Type 1 ¡V Open Sea Disposal) , m3

Nil

10375

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

Nil

16261

East of Cha Chau

South Brothers

           

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.4.2.     Inert C&D & non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.18.

Table 5.18   Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

4

456338.412

TKO137 / TM 38

Inert C&D materials recycled, m3

Nil

46520

N/A

Non-inert C&D materials disposed, m3

83

2253.317

SENT Landfill

Non-inert C&D materials recycled, m3

Nil

N/A

N/A

Chemical waste disposed, kg

Nil

18253

SENT Landfill

Marine Sediment (Type 1 ¡V Open Sea Disposal) , m3

Nil

27889

South Cheung Chau

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under

FEP-05/364/2009/A

 

5.4.3.     Inert C&D and non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.19  Details of Waste Disposal for Contract no. HY/2009/18

Waste Type

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

2291.41

167085.381

T.K.O. 137, TM 38

Inert C&D materials recycled, m3

Nil

58787.05

N/A

Non-inert C&D materials disposed, m3

55.91

3780.316

SENT Landfill

Non-inert C&D materials recycled, ton

2.16

878.37

N/A

Chemical waste disposed, kg

Nil

4440

N/A

 

 

 

 

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

5.4.4.     Inert & Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.

Table 5.20   Details of Waste Disposal for Contract no. HY/2009/15

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

13568

33.4

618555.47

251284.7

Tuen Mun Area 38

TKO137 FB

 

Inert C&D materials recycled, m3

Nil

358660.77

HY/2009/11

ex-PCWA

TS4 /TS2

WDII

Lun Ku Tan

WENT

Non-inert C&D materials disposed, m3

171.3

3585.13

SENT Landfill

Non-inert C&D materials recycled, m3

Nil

5496446.2

Xun Xiang Metalware Skylight Recycle (paper)

Chemical waste disposed, kg

Nil

22755

 

Dunwell Group

 

Marine Sediment (Type1-Open Sea Disposal (Dedicate Sites) &Type 2 ¡V Confined Marine Disposal), m3

Nil

5684

South of the Brothers

          

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

5.4.5.     Inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.21.

Table 5.21   Details of Waste Disposal for Contract no. HY/2009/19

Waste Type*

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

1570.56

631820.51

N/A

Inert C&D materials recycled, m3

Nil

81822.39

N/A

Non-inert C&D materials disposed, m3

102.07

4138.62

SENT Landfill

Non-inert C&D materials recycled, m3

15.22

482.63

N/A

Chemical waste disposed, kg

                 Nil

9.69

N/A

Marine Sediment (Tunnel) (Type-1 Open Sea Disposal), m3

Nil

20556

South of Cheung Chau

Marine Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 ¡V Confined Marine Disposal), m3

Nil

30751

East of Sha Chau

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

5.4.6.     No inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.22.

Table 5.22  Details of Waste Disposal for Contract no. HK/2012/08

Waste Type*

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

8694

114114

TKO 137

Inert C&D materials recycled, m3

581

36107

N/A

Non-inert C&D materials disposed, m3

85

940

SENT

Non-inert C&D materials recycled, m3

Nil

Nil

N/A

Chemical waste disposed, kg

Nil

Nil

N/A

Marine sediment (Type 1) disposal, m3

Nil

3145

South of Cheung Chau / East of Sha Chau / South of The Brothers

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2010/08 Central ¡V Wan Chai Bypass (CWB) ¡V Tunnel (Slip Road 8) under FEP-10/364/2009/B

5.4.7.     No inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.23.

Waste Type*

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

21,511

21

396,504

410

TM 38

TKO 137

Inert C&D materials recycled, m3

Nil

Nil

N/A

Non-inert C&D materials disposed, m3

                73

1355

SENT

Non-inert C&D materials recycled, m3

Nil

Nil

N/A

Chemical waste disposed, kg

Nil

979

N/A

Table 5.23  Details of Waste Disposal for Contract no. HY/2010/08

 

 

 

 

 

 

 

 

 

 

 

 

    

 

Remarks: The cumulative quantity for inert C&D materials disposed and the inert C&D material recycled under Contract HY/2010/08 subject to further clarified upon RSS confirmation.

Contract no. HY/2011/08 Central ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

5.4.8.     No inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.24.

Table 5.24  Details of Waste Disposal for Contract no. HY/2011/08

Waste Type*

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

75.6

331.87

CWPF & TKO137

Inert C&D materials recycled, m3

Nil

Nil

N/A

Non-inert C&D materials disposed, m3

52.51

488.84

SENT

Non-inert C&D materials recycled, ton

Nil

31.72

N/A

Chemical waste disposed, kg

Nil

3800

N/A

 

6.0        Compliance Audit

6.0.1.     The Event Action Plan for construction noise, air qualities are presented in Appendix 6.1.

6.1          Noise Monitoring

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

 

6.1.1.     No exceedance was recorded in the reporting month.

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

6.1.2.     Four limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 01, 08, 15 and 23 December 2015 in this reporting month.

6.1.3.     Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 01, 08, 15 and 23 December 2015.  As such, the exceedance was considered as non-Project related.

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.1.4.     Four limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 01, 08, 15 and 23 December 2015 in this reporting month.

6.1.5.     Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 01, 08, 15 and 23 December 2015.  As such, the exceedance was considered as non-Project related.

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

6.1.6.     No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

6.1.7.     Two limit level exceedances were recorded at M6 ¡V HK Baptist Church Henrietta Secondary School on 11 and 16 December 2015.

6.1.8.     Investigations found that on 11 and 16 December 2015, traffic noise were major contribution in the noise monitoring and exceedances were not related to the Project.

 

 

Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B

 

6.1.9.     No exceedance was recorded in the reporting month.

Contract no. HY/2011/08 Central ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

6.1.10.   No exceedance was recorded in the reporting month.

 

 

 

Real Time Noise Monitoring

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

6.1.11.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

6.1.12.   Limit level exceedance was recorded at RTN2a-Electric Centre on 15 December 2015 during daytime in the reporting month. On 15 December 2015, concreting was undertaken by Contract HY/2009/19 while steel bar cutting works by saw cutter for Hong Kong Electric Centre was conducted at the roof top by non-CWB Contractor immediately next to the noise monitoring station and was considered as major noise contribution. As such, the exceedance was considered as non-Project related.

6.1.13.   No limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School during in the reporting month.

6.1.14.   Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre during daytime on 02 December 2015 in the reporting month. On 02 December 2015, only steel mould dismantling works was undertaken by Contract HY/2009/19 during monitoring while scaffold dismantling and manual handling of material was observed undertaken by non-CWB Contractor at Causeway Bay Community Centre in close proximity to the monitoring station and was considered as the major noise contribution. As such, the exceedances were considered as non-Project related.

Contract no. HY/2011/08 Central ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

6.1.15.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

6.2          Air Quality Monitoring

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

6.2.1.     No exceedance was recorded in the reporting month.

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

6.2.2.     No exceedance was recorded in the reporting month.

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.2.3.     No exceedance was recorded in the reporting month.

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

6.2.4.     No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

6.2.5.     No exceedance was recorded in the reporting month.

Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

6.2.6.     No exceedance was recorded in the reporting month.

Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B

6.2.7.     No exceedance was recorded in the reporting month.

Contract no. HY/2011/08 Central ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

6.2.1       No exceedance was recorded in the reporting month.

6.3          Review of the Reasons for and the Implications of Non-compliance

6.3.1.     There was no non-compliance from the site audits and monitoring in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.4          Summary of action taken in the event of and follow-up on non-compliance

6.4.1       There was no particular action taken since no non-compliance was recorded from the site audits and monitoring in the reporting period.

 

7.0        Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-364/2009/C, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.     According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011.  As such, it is considered that there were no cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) undertaken by contractor HK12/02 in the reporting month.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area include caisson seawall installation, ELS works, road works and drainage works and Road P1 pedestrian road reinstatement were performed in December 2015 reporting month. As no project related exceedance were recorded during the reporting period, cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was considered as insignificant. 

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activities under Wan Chai Development Phase II were tunnel works, ELS works and road works at Wan Chai East and caisson installation, D-wall construction and ELS works at Wan Chai West. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were bridge construction and road works at Central Interchange, ELS works at Ex-PCWAW, ELS works and retaining wall construction at Victoria Park; D- wall construction, ELS works and tunnel works at TS3; IEC removal works and tunnel works at North Point area in the reporting month. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects was observed undertaken at Wan Chai North area.

7.0.5.     No significant air quality impact from construction activities was anticipated in the reporting month. Besides, no project related exceedance was recorded during the air quality and noise environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was insignificant.

8.0            Enviromental site audit

8.0.1.           During this reporting month, weekly environmental site audits were conducted for Contracts no. HY/2009/15, HY/2009/18, HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02, HY/2010/08 and HY/2011/08. No non-conformance was identified during the site audits. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

8.0.2.           Four site inspections for Contract no. HY/2009/15 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.1.

Table 8.1     Summary of Environmental Inspections for Contract no. HY/2009/15

Item

Date

Observations

Action taken by Contractor

Completion date

151209_1

9-Dec-2015

Review the conditioning and coagulant dosage applied to ensure no turbid discharge

(EX-PCWAW)

No further turbid discharge was observed

Completed as observed on 15 December 2015

151215_1

15-Dec-2015

Discharge point of washing sink shall be connected to waste water treatment plant

(EX-PCWA East)

Discharge point of washing sink has been connected to collection pit

(EX-PCWA East)

Completed as observed on 22 December 2015

 

8.0.3.           Five site inspections for Contract no. HY/2009/18 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.2.

Table 8.2     Summary of Environmental Inspections for Contract no. HY/2009/18

Item

Date

Observations

Action taken by Contractor

Completion date

151210_2

10-Dec-15

Idle stockpile shall be covered properly to prevent dust emission (Man Chiu Street)

Covering and watering has been provided to stockpile

Completion as observed on 17 Dec 2015

 

 

 

 

 

 

 

8.0.4.           Four site inspections for Contract no. HY/2009/19 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.3.

Table 8.3     Summary of Environmental Inspections for Contract no. HY/2009/19

Item

Date

Observations

Action taken by Contractor

Completion date

151202_1

02-Dec- 2015

Noise barriers provided to construction of substructure works shall installed according to EP condition

(Portion III)

No further construction of substructure was observed and the barrier was installed as per requirement

Completion as observed on 21 December 2015

 

8.0.5.           Four site inspections for Contract no. HK/2009/01 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.4

Table 8.4     Summary of Environmental Inspections for Contract no. HK/2009/01

Item

Date

Observations

Action taken by Contractor

Completion date

151202_01

2-Dec-15

Drip tray shall be provided for oil container at slip road 3

Oil container has been removed and disposed.

Completion as observed on 9 December 2015

151209_01

9/12/2015

Drip tray shall be provided to oil container

(Stage 1)

Oil container has been removed and disposed.

Completion as observed on 17 December 2015

 

8.0.6.           Four site inspections for Contract no. HK/2009/02 was carried out during this reporting period. No observation was found in the reporting month. The results of these inspections and outcomes are summarized in Table 8.5.

         Table 8.5     Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Completion date

151203_01

3-Dec-15

Hole of drip tray under mechanical pump shall be covered at WCR3

The hole of drip tray has been covered at WCR3.

Completion as observed on 10 December 2015.

151203_02

3-Dec-15

The gap of silt curtain at RW21-P789 shall be minimized to properly maintain the silt curtain condition.

Silt curtain at RW21-P789 has deployed to seabed level.

Completion as observed on 16 December 2015.

151203_03

3-Dec-15

Silt above the seawall block shall be cleaned to prevent any surface runoff during the coming rainstorm at WCR3.

Silt above the seawall block was cleaned at WCR3.

Completion as observed on 10 December 2015.

8.0.7.            Four site inspection for Contract no. HK/2012/08 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.6

Table 8.6     Summary of Environmental Inspections for Contract no. HK/2012/08

Item

Date

Observations

Action taken by Contractor

Completion date

151208_01

8-Dec-15

Floating refuse shall be collected at Zone A2 area.

Floating refuse was cleared at Zone A2.

Completion as observed on 15 December 2015

151208_02

8-Dec-15

Silt curtain at the opening of water channel shall be repaired and properly maintain.

Silt curtain was repaired and properly deployed.

Completion as observed on 15 December 2015

151222_01

22-Dec-15

Muddy effluent at site exit and public road shall be cleaned regularly in an orderly manner.

The site exit and public road were cleaned properly.

Completion as observed on 29 December 2015

151222_02

22-Dec-15

Direct discharge from boxes was observed at water channel, contaminated effluent shall be collected in proper manner and treated before discharge.

Discharge was stopped and no further discharge was observed.

Completion as observed on 22 December 2015

 

 

 

 

 

 

 

 

 

 

 

 

 

Item

Date

Observations

Action taken by Contractor

Completion date

151202_1

2-Dec-15

Piping with ide ends shall be removed to avoid potential discharge (TS3)

Idle pipes were removed

Completion as observed on 3 December 2015

151202_2

2-Dec-15

The contractor shall critically review the storage holding tank to avoid overflow to nearby water (TS3)

The holding tank of concern was abandon from used.

Completion as observed on 9 December 2015

151202_3

2-Dec-15

Review the dosage and operation of waste water treatment plant to avoid turbid discharge (TS3)

No further turbid discharge was observed

Completion as observed on 3 December 2015

151202_4

2-Dec-15

Effluent pipe from the desilting compartment of the waste water treatment plant shall be properly connected to a collection pit or disconnected (TS3)

The piping from the desilting compartment was stored properly to avoid accidental discharge.

Completion as observed on 14 December 2015

151202_5

2-Dec-15

Clean the leaked oil as chemical waste (TS3)

Leaked oil has been cleared

Completion as observed on 3 December 2015

151203_1

3-Dec-15

Damaged barrier around site boundary shall be repaired (Victoria Park)

Damaged barrier was repaired

Completion as observed on 9 December 2015

151203_2

3-Dec-15

Drip tray shall be provided for chemical containers

The chemical container was removed

Completion as observed on 9 December 2015

151209_1

9-Dec-15

Clear the soil deposit at the boundary of site location to prevent direct wash off of contaminated effluent

(TS3 North)

Mud residue deposited has been cleared

Completion as observed on 16 December 2015

151209_2

9-Dec-15

Tarpaulin sheet shall be provided/reinstated after repositioning of barge prior to resumption of excavated material transfer to prevent drop off

The tarpaulin sheeting was rearranged at proper position for excavated material transfer

Completion as observed on 11 December 2015

151211_1

11-Dec-15

Contractor was advised to clean the mud deposit within waste water treatment plant before resumption of plant operation to avoid discharge contamination (Victoria Park)

The mud residue within the treatment unit was cleared

Completion as observed on 14 December 2015

8.0.8.           Eight site inspections for Contract no. HY/2010/08 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.7

Table 8.7     Summary of Environmental Inspections for Contract no. HY/2010/08

 


 

151211_2

11-Dec-15

Review the adequacy of the barrier in height to ensure sufficient height of 2.4m (Victoria Park)

The condition of the barrier was improve.

Completion as observed on 14 December 2015

151211_3

11-Dec-15

Clear the floating scum around works boundary (TS3)

Floating refuse have been cleared

Completion as observed on 14 December 2015

151211_4

11-Dec-15

Provide drip tray for chemical container (Victoria Park Road)

The chemical container was removed

Completion as observed on 14 December 2015

151214_1

14-Dec-15

Provide watering to breaking works (TS3)

No further concerned breaking works was observed

Completion as observed on 16 December 2015

151216_1

16-Dec-15

Critical review the capacity and operation of waste water treatment plant and avoid potential turbid discharge (TS3 West)

No further turbid discharge was observed

Completion as observed on 22 December 2015

151216_2

16-Dec-15

Drip tray shall be provided to oil containers (TS3)

Oil container was removed

Completion as observed on 31 December 2015

151224_1

24-Dec-15

Fine particular was observed at the outlet tank of the wastewater treatment system. The contractor was advised to review the operation condition and dosage and recirculate for treatment before discharge (TS3 West)

No further fine particulates were observed

Completion as observed on 29 December 2015

151224_2

24-Dec-15

Clean the mud/silt deposition to ensure proper settling prior to resuming the plant operation (Victoria Park)

The mud deposition was cleared

Completion as observed on 29 December 2015

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

8.0.9.     Four site inspections for Contract no. HY/2011/08 were carried out during this reporting period. No observation was found in the reporting month.    

9.0        Complaints, Notification of Summons and Prosecution

9.0.1.     Two environmental complaints were received in the reporting month.

9.0.2.     First public complaint regarding construction dust impact referred by EPD was received by ET on 04 December 2015 (EPD Ref: H04/RS/00028924-15). The complainant reported that excessive construction dust was generated from the construction site near Two International Finance Centre at Finance Street, Central

 

ET confirmed with the Resident Site Staff that bridge works and drains/ sewers construction at the concerned location was undertaken by Contract HY/2009/18 on 12 November 2015.  A stockpile which would be reused for backfilling was stored at the concerned location by Contract HY/2009/18 on 12 November 2015.

 

Mitigation measures implemented by the Contractor for the above construction works including covering of idled portion of stockpile and dampening of the exposed stockpile was implemented for the stockpile at the concerned location.

 

According to relevant site records confirmed by RSS, bridge works and drains/ sewers construction at the concerned location was undertaken by Contractor of HY/2009/18 on 12 November 2015 and a stockpile which would be reused for backfilling was stored at the concerned location. Mitigation measures including covering of idled portion of stockpile and dampening of the exposed stockpile was implemented for the stockpile at the concerned location.

 

In view of the public concern on potential dust impact at the concerned location, the Contractor of HY/2009/18 rearranged the works sequence and placed concrete blocks at the bridge retaining wall to allow for early commencement of backfilling on 19 November 2015 to minimize the size of the stockpile at an earlier stage. Additional water sprinklers were installed on 27 November 2015 to further enhance the dampening of the stockpile surface during excavation.

 

Follow-up inspection was conducted during weekly environmental inspection on 10 December 2015 and mitigation measures including covering of stockpile stored at the concerned location was implemented while it was observed that stockpiles stored near Man Chiu Street was not properly covered. The Contractor of HY/2009/18 was advised to promptly provide covering to all idled stockpile stored on site and the Contractor was reminded to enhance the watering during excavated material handling near the concerned location. Further follow up inspection was conducted on 17 December 2015 and mitigation measures including covering and watering for idle stockpile and material handling were implemented.

 

9.0.3.     Second public complaint regarding noise impact referred by RSS was received by ET on 16 December 2015 (ICC Case Ref.: 2-1656689815 dated 14 December 2015). The complainant reported that incessant noise emanating from the construction site of the Island Eastern Corridor Link that forms part of the Central-Wanchai Bypass Project.

 

Over the past couple of weeks, there have been loud mechanical pounding at the construction site over the reclaimed area between Blocks 10 and 11 of City Garden. As can be seen, machines have been breaking open the concrete paved on top of the reclaimed area. Work often starts well before 9am on weekdays and, barring a brief period of lull during lunch hours, would often continue unabated until after 5pm. Although I note that certain noise reduction measures have been put into place (e.g. the erection of flimsy noise barriers around the work area), the noise created is still enormous, and this has become a significant nuisance for residents living in nearby blocks of our estate, especially children and the elderly who have to stay at home for longer hours.

 

ET confirmed with the Resident Site Staff that concreting breaking works was carried out with one breaker on 7, 9, 11, 12 and 14 December 2015 and the breaking works at the concerned location were completed on 14 December 2015 morning. Noise mitigation measures including temporary noise barriers near the point of breaking and covering the breaker with acoustic mat were provided during the concerned concrete breaking works.

 

According to information confirmed by RSS, concreting breaking works was carried out by one excavator mounted breaker on 7, 9, 11, 12 and 14 December 2015 and the concerned breaking works outside City Garden Block 10 and Block 11 was completed on 14 December 2015 morning. Noise mitigation measures including temporary noise barriers near the point of breaking and covering the breaker with acoustic mat were provided during the concerned concrete breaking works. Based on the further review on the record of the environmental inspection conducted on 09 December 2015, the Contractor of HY/2009/19 was reminded to temporary noise barrier provided for the pile cap demolition shall follow the Environmental Permit EP-364/2009/D requirement.

 

Follow up inspection was conducted during weekly environmental inspection on 17 December 2015, the concerned breaking works opposite to City Garden Block 10 and Block 11 was observed completed while the Contractor was reminded that the remaining section of temporary noise barrier in accordance with the latest Environmental Permit EP-364/2009/D shall be completed on site as soon as possible. According to the information provided by RSS, the temporary noise barrier in accordance with the Environmental Permit requirement opposite to City Garden was substantially completed on 21 December 2015. In view of the public concern, the Contractor was suggested to consider to review the works duration at daytime and conduct other future breaking works around the concerned location intermittently to minimize the potential noise nuisance caused to the surroundings.

9.0.4.     Referring to the complaint case regarding the illegal disposal of construction waste referred by EPD was received by ET on 17 November 2015, the updated 2nd and 3rd interim investigation report were submitted to the EPD on 17 December 2015 and 31 December 2015 respectively. In response to the complaint concern, additional water quality monitoring and additional site inspections have been conducted by the ET and the investigation findings were included in the interim investigation reports separately submitted to the EPD. In addition, the ET and IEC have conducted checking on the waste disposal records and site construction records with the CWB RSS team to confirm the key construction activities during the concerned period and the quantities of inert C&D material disposed. Upon further review on relevant records and follow up inspections on the implementation of site measures, the final investigation would be issued.

9.0.5.     The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.6.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

December 2015

2

September 2010 ¡V November 2015

51

Total

53

 

 

Table 9.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

10         Conclusion

10.0.1.   The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.   The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1. The construction programmes of individual contracts are provided in Appendix 10.1.

Table 10.1  Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

Contract No.

Key Construction Works

Recommended Mitigation Measures

HY/2009/15

¡P         Remedial works at Mined Tunnel

¡P         Excavation and RC structure works at TPCWAW

¡P         Remaining works inside tunnel at TS4 and TPCWAE

¡P         Removal of standby Dewatering System and monitoring instrument along Hung Hing road

 

 

¡P         Dust control during dust generating activities

¡P         Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system or the nearby water.

 

HY/2009/18

¡P         Drainage works

¡P         Road works

¡P         Bridges construction

 

¡P         Dust control during dust generating activities

¡P         Provide protection works to ensure no runoff out of site area or direct discharge into public drainage system.

 

HY/2009/19

¡P         Pier construction for IEC

¡P         Construction of EVB

¡P         Column modification at F1 to F8

¡P         Watson Road laying of new water pipe

¡P         Oil Street drainage works

¡P         Excavation / Construction of retaining wall/Approach Ramp/ADB

¡P         Bridge segment erections

¡P         Pre-bored H-pile for Approach Ramp

¡P         Hing Fat Street modification works

¡P         Bridge TA2 demolition

¡P         Abutment D12 construction

 

¡P         Noise level shall be controlled by reducing the breaking operation rate.

¡P         Noise barrier shall be implemented

¡P         Dust control during dust generating works

¡P         Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system or the sea.

HK/2009/01

¡P         Stage 1 ,2 & 3 Backfilling works at CWB Tunnel top slab

¡P         Stage 2 Construction of slip road 3

¡P         Stage 3 RC structure for CWB Tunnel Bay 18 to 20

¡P         Removal of abandoned cooling main (P7/P9) at Convention Avenue

¡P         Reinstatement of outfall

¡P         Reinstatement of triangular planter at Fenwick Pier Street

¡P         Roadworks /drains for Expo Drive East

¡P         Stage 4 ELS works

 

¡P         Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system or the sea.

¡P         Dust control during dust generating works

HK/2009/02

¡P         Completion of road side barriers

¡P         Backfilling works

¡P         Cutting the top part of diaphragm wall

¡P         Strut layer S6 lateral support installation

¡P         Breaking through bulkhead wall BW3

¡P         Pouring blinding layer concrete

¡P         Tunnel construction at west side

¡P         Waterproofing layer application

¡P         Ground investigation works for bored piles and diaphragm wall

¡P         Bored pile construction

¡P         Pre-treatment works and guide wall construction for diaphragm wall

¡P         Diaphragm wall construction

¡P         Extraction of the temporary sheetpile seawall and removal of the temporary seawall blocks near the interface between Portion 2 and Portion 5

 

¡P         Dust control during dust generating works

¡P         Provision of protection to ensure no runoff out of site area or direct discharge into public drainage system.

HK/2012/08

¡P         Diaphragm wall construction

¡P         Grouting

¡P         Construction of MVB

¡P         Pre-bored H-pile construction

¡P         Construction of concrete plug

¡P         Excavation and lateral support installation

 

¡P         Dust control during dust generating works

¡P         Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system.

HY/2010/08

¡P         Tree protection works next to existing BGO,

¡P         Drainage improvement works,

¡P         Sheet piling works,

¡P         Excavation and Lateral Support for U-structure,

¡P         Pipe piling & grouting works,

¡P         Utility diversion works,

¡P         Retaining wall works

¡P         ELS works,

¡P         Diaphragm Wall, Barrette construction and king post installation works

¡P         D-wall drill cutting works

¡P         Construction works for subway extension

 

¡P         Dust control during dust generating works

¡P         Appropriate measures should be taken to ensure adequate protections are provided for trees being transplanted and retained on site.

¡P         Provision of protection to ensure no runoff out of site area or direct discharge into public drainage system.

 

HY/2011/08

¡P         West Ventilation Building Construction

¡P         East Ventilation Shaft Construction

¡P         Tunnel Thermal Barrier Construction

 

¡P         Dust control during dust generating works

 

 

10.0.3.   The construction works of Contract no. 04/HY/2006 ¡V Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by the Contractor on 11 February 2011.

10.0.4.   The construction works of Contract no. HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was completed, and the FEP was surrendered by the Contractor and found in order by EPD on 25 April 2013.

10.0.5.   The construction works of Contract HK/2010/06 was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.